78.There may be valid reasons why a contracting authority does not intend to include social public works clauses in major construction contracts. This section requires a contracting authority to notify the Welsh Ministers if, in relation to a major construction contract—

a.

it does not intend to include the social public works clauses, or

b.

despite taking reasonable steps to include them, they are not contained in a contract.

79.A contracting authority must also inform the Welsh Ministers if it has failed to pass the required obligation through supply chains via subcontracts, or has not put a process in place to manage their implementation.

80.A notification must be made as soon as possible giving the authority’s reasons.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of Senedd Cymru.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources