Search Legislation

Water Industry Act 1991

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As enacted)
 Help about advanced features

Advanced Features

Changes over time for: Section 117E

 Help about opening options

Alternative versions:

Changes to legislation:

Water Industry Act 1991, Section 117E is up to date with all changes known to be in force on or before 07 May 2024. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Act associated Parts and Chapters:

Whole provisions yet to be inserted into this Act (including any effects on those provisions):

[F1117EAgreements as to duties under sections 117A to 117DE+W

(1)On the application of—

(a)a sewerage licensee that has made a request under sections 117A to 117D, or

(b)a sewerage undertaker to which such a request has been made,

the Authority may by order require a sewerage undertaker to perform the duty in question under sections 117A to 117D, for such period and on such terms and conditions as may be specified in the order.

(2)The Authority may make an order under subsection (1) only if—

(a)it appears to the Authority that the sewerage undertaker is required to perform the duty in question, and

(b)it is satisfied that the parties cannot reach agreement within a reasonable time.

(3)An order under subsection (1) has effect as an agreement between—

(a)the sewerage licensee, and

(b)the sewerage undertaker required to perform the duty in question.

(4)On the application of a party to a section 117E agreement, the Authority may, if it is satisfied that the parties cannot reach agreement on the variation or termination of the agreement, by order vary or terminate the agreement.

(5)If an order under subsection (4) is made in relation to a section 117E agreement, the agreement—

(a)has effect subject to the provision made by the order, or

(b)ceases to have effect, as the case may be.

(6)An order under subsection (4) may require one party to the agreement to pay compensation to the other.

(7)Neither the CMA nor the Authority may exercise, in respect of an agreement for the performance of a duty under sections 117A to 117D by a sewerage undertaker, the powers conferred by—

(a)section 32 of the Competition Act 1998 (directions in relation to agreements);

(b)section 35(2) of that Act (interim directions).

(8)Subsection (7)(b) does not apply to the exercise of powers in respect of conduct—

(a)which is connected with an agreement for the performance of a duty under sections 117A to 117D by a sewerage undertaker, and

(b)in respect of which section 35(1) of the Competition Act 1998 applies because of an investigation under section 25 of that Act relating to a suspected infringement of the Chapter 2 prohibition imposed by section 18(1) of that Act.

(9)In this Chapter a reference to a section 117E agreement is a reference to—

(a)an agreement for the performance of a duty under sections 117A to 117D by a sewerage undertaker, or

(b)an order deemed to be such an agreement under subsection (3), or

(c)an agreement varied by order under subsection (4).]

Textual Amendments

F1Pt. 4 Ch. 2A inserted (1.9.2015 for the insertion of s. 117G (except s. 117G(2)(e)(7)), 1.9.2015 for the insertion of s. 117K (except s. 117K(2)(e)(8)), 1.4.2016 for the insertion of ss. 117G(2)(e), 117P(4), 117R, 117S, 1.9.2016 for the insertion of ss. 117I for specified purposes, 117J, 117K(2)(e)(8), 117L, 30.3.2017 for the insertion of s. 117G so far as not already in force and ss. 117F, 117H) by Water Act 2014 (c. 21), s. 94(3), Sch. 4; S.I. 2015/773, art. 3(d) (with art. 5); S.I. 2015/1469, art. 3(e); S.I. 2016/465, arts. 2(k), 3(f) (with Sch. 2) (as amended (22.3.2017) by S.I. 2017/462, art. 16); S.I. 2017/462, art. 2(d)

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources