The East Anglia ONE North Offshore Wind Farm Order 2022

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: PART 1

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for the The East Anglia ONE North Offshore Wind Farm Order 2022, PART 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 1E+W+SDocuments forming the environmental statement to be certified

Commencement Information

I1Sch. 17 Pt. 1 in force at 22.4.2022, see art. 1(2)

(1)(2)(3)(4)(5)

Document Reference

(and relevant ES Chapters)

Examination Library Reference

(and relevant ES Chapter reference)

Document NameVersionDate
6.1APP-049 to APP-079Environmental Statement125 October 2019
6.2APP-080 to APP-441Figures125 October 2019
6.3APP-442 to APP-571Technical Appendices125 October 2019
ExA.WQ-1.A10.D1.V1 (Chapter 6)

REP1-099

(APP-054)

Applicants’ Responses to WQ1 Appendix 10 Landfall Indicative HDD Working Area1

Deadline 1

2 November 2020

ExA.WQ-1.A11.D1.V1

(Chapter 6)

REP1-100

(APP-054)

Applicants’ Responses to WQ1 Appendix 11 Landfall HDD Cross Sections1

Deadline 1

2 November 2020

ExA.AS-13.D6.V1

(Chapter 6)

REP6-024

(APP-054)

HDD Verification Clarification Note1

Deadline 6

24 February 2021

ExA.WQ-1.A6.D1.V1

(Chapter 6)

REP1-090

(APP-054)

Applicants’ Responses to WQ1 Appendix 6 Illustrative Open Trench and Trenchless Onshore Cable Route1

Deadline 1

2 November 2020

ExA.WQ-1.A7.D1.V1

(Chapter 6)

REP1-091

(APP-054)

Applicants’ Responses to WQ1 Appendix 7 Onshore Crossing Schedule1

Deadline 1

2 November 2020

ExA.AS-10.D3.V1

(Chapter 6)

REP3-056

(APP-054)

Onshore Cable Route Works Programme Clarification Note1

Deadline 3

15 December 2020

ExA.AS-11.D3.V1

(Chapter 6)

(Chapter 29)

REP3-057

(APP-054)

(APP-077)

Onshore Substations Update Clarification Note1

Deadline 3

15 December 2020

ExA.AS-12.D3.V1

(Chapter 6)

REP3-058

(APP-054)

Construction in Proximity to Properties1

Deadline 3

15 December 2020

6.3.6.2

(Chapter 6)

REP8-015

(APP-054)

EA1N Environmental Statement Appendix 6.2 Relationship of Onshore Plans Secured by the DCO5

Deadline 8

25 March 2021

6.3.6.3

(Chapter 6)

REP8-016

(APP-054)

EA1N Environmental Statement Appendix 6.3 Relationship of Offshore Plans Secured by the DCO5

Deadline 8

25 March 2021

6.3.6.4

(Chapter 6)

REP3-020

(APP-054)

EA1N Environmental Statement Appendix 6.4 Cumulative Project Description2

Deadline 3

15 December 2020

ExA.RRA6.D0.V1

(Chapters 7 to 17)

AS-043

(APP-055 to APP-065)

[F1Applicant’s Comments on Relevant Representations] F2... Appendix 6 Disposal Site Locations (Windfarm Site)111 June 2020

ExA.RRA2.D0.V1

(Chapter 7)

AS-039

(APP-055)

[F1Applicant’s Comments on Relevant Representations] F2... Appendix 2 Wave Climatology Clarification Note111 June 2020

ExA.AS-13.D3.V1

(Chapter 7)

(Chapter 9)

(Chapter 10)

(Chapter 12)

REP3-059

(APP-055)

(APP-057)

(APP-058)

(APP-060)

Effects on Supporting Habitats of Outer Thames Estuary SPA Clarification Note1

Deadline 3

15 December 2020

ExA.RRA3.D0.V1

(Chapter 10)

AS-040

(APP-058)

[F1Applicant’s Comments on Relevant Representations] F2... Appendix 3 Fish and Shellfish Ecology Clarification Note111 June 2020

ExA.AS-5.D11.V2

(Chapter 11)

REP11-045

[F1(APP-059)]

Underwater Noise Modelling [F3Report Update] Update2

Deadline 11

7 June 2021

ExA.AS-3.D2.V1

(Chapter 12)

REP2-006

(APP-060)

Cumulative Auk Displacement [F4and], Seabird Assemblage Assessment of FFC SPA and Gannet PVA1

Deadline 2

17 November 2020

ExA.AS-2.D11.V5 (Chapter 12)REP11-026 (APP-060)Displacement of red-throated divers in the Outer Thames Estuary SPA5

Deadline 11

7 June 2021

ExA.AS-20.D1.V1

(Chapter 19)

(Chapter 26)

REP1-040

(APP-067)

(APP-074)

Deadline 1 Air Quality Clarification Note1

Deadline 1

2 November 2020

ExA.AS-16.D3.V1

(Chapter 19)

REP3-061

(APP-067)

Deadline 3 Air Quality Clarification Note1

Deadline 3

15 December 2020

ExA.WQ-1.A8.D1.V1

(Chapter 20)

REP1-092

(APP-068)

Applicants’ Responses to WQ1 Appendix 8 Environment Agency Flood Zones1

Deadline 1

2 November 2020

ExA.AS-9.D4.V2

(Chapter 20)

REP4-044

(APP-068)

[F3Clarification Note] SuDS Infiltration Note2

Deadline 4

13 January 2021

ExA.AS-12.D6.V1

(Chapter 18)(Chapter 20)

REP6-021

(APP-066)

(APP-068)

Landfall Hydrogeological Risk Assessment1

Deadline 6

24 February 2021

ExA.AS-13.D8.V1

(Chapter 20)

REP8-038

(APP-068)

Flood Risk and Drainage Clarification Note1

Deadline 8

25 March 2021

ExA.AS-11.D1.V1

(Chapter 21)

REP1-022

(APP-069)

Land Use Clarification Note1

Deadline 1

2 November 2020

ExA.WQ-1.A4.D1.V1

(Chapter 22)

REP1-088

(APP-070)

Applicants’ Responses to WQ1 Appendix 4 Ecological Mitigation Works1

Deadline 1

2 November 2020

ExA.AS-12.D1.V1

(Chapter 22)

REP1-023

(APP-070)

Onshore Ecology Clarification Note1

Deadline 1

2 November 2020

ExA.AS-16.D1.V1

(Chapter 22)

REP1-035

(APP-070)

Ecological Enhancement Clarification Note1

Deadline 1

2 November 2020

ExA.AS-14.D3.V1

(Chapter 22)

REP3-060

(APP-070)

Deadline 3 Onshore Ecology Clarification Note1

Deadline 3

15 December 2020

ExA.AS-10.D4.V1

(Chapter 22)

REP4-005

(APP-070)

Deadline 4 Onshore Ecology Clarification Note1

Deadline 4

13 January 2021

ExA.AS-14.D6.V1

(Chapter 22)

REP6-025

(APP-070)

Deadline 6 Onshore Ecology Clarification Note1

Deadline 6

24 February 2021

ExA.AS-28.D6.V1

(Chapter 22)

REP6-035

(APP-070)

Ecology Survey Results: February 20211

Deadline 6

24 February 2021

ExA.AS-16.D8.V1

(Chapter 22)

REP8-041

(APP-070)

Ecological Enhancement Clarification Note Addendum1

Deadline 8

25 March 2021

ExA.AS-10.D1.V1

(Chapter 24)

(Chapter 29)

REP1-021

(APP-072)

(APP-077)

Archaeology and Cultural Heritage Clarification Note1

Deadline 1

2 November 2020

ExA.AS-13.D1.V1

(Chapter 24)

REP1-024

(APP-072)

Pre-Construction Trial Trenching Report1

Deadline 1

2 November 2020

ExA.AS-14.D1.V1

(Chapter 24)

REP1-025 to REP1-033

(APP-072)

Onshore Archaeology Geophysical Survey Report (Parts 1 to 9)1

Deadline 1

2 November 2020

ExA.AS-15.D1.V1

(Chapter 24)

REP1-034

(APP-072)

Onshore Archaeology Earthworks Report1

Deadline 1

2 November 2020

ExA.AS-29.D8.V1

(Chapter 24)

REP8-063

(APP-072)

Cultural heritage Viewpoint 5 Additional Visualisation1

Deadline 8

25 March 2021

ExA.AS-16.D3.V1

(Chapter 24) (Chapter 29)

REP3-062 to REP3-068

(APP-072)

(APP-077)

Updated Photomontages Clarification Note1

Deadline 3

15 December 2020

ExA.AS-11.D4.V1

(Chapter 24)

REP4-006

(APP-072)

Heritage Assessment Addendum1

Deadline 4

13 January 2021

ExA.AS-11.D4.V1_001

(Chapter 24)

REP4-007

(APP-072)

Heritage Assessment Addendum Appendix 1 CHVP2 –PRoW between Friston Hall and Friston (Appendix 24.7, Figure 7 Update) [F51]

Deadline 4

13 January 2021

ExA.AS-11.D4.V1_002

(Chapter 24)

REP4-008

(APP-072)

Heritage Assessment Addendum Appendix 2 CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8 Update) [F51]

Deadline 4

13 January 2021

ExA.AS-11.D4.V1_003

(Chapter 24)

REP4-009

(APP-072)

Heritage Assessment Addendum Appendix 3 CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9 Update) [F51]

Deadline 4

13 January 2021

ExA.AS-11.D4.V1_004

(Chapter 24)

REP4-010

(APP-072)

Heritage Assessment Addendum Appendix 4 CHVP5 – PRoW at Woodside Farm (Appendix 24.7, Figure 10 Update) [F51]

Deadline 4

13 January 2021

ExA.AS-11.D4.V1_005

(Chapter 24)

REP4-011

(APP-072)

Heritage Assessment Addendum Appendix 5 CHVP7 – Friston House (b) (Appendix 24.7, Figure 12 Update) [F51]

Deadline 4

13 January 2021

ExA.AS-11.D4.V1_006

(Chapter 24)

REP4-012

(APP-072)

Heritage Assessment Addendum Appendix 6 CHVP8 – Friston War Memorial (Appendix 24.7, Figure 13 Update) [F51]

Deadline 4

13 January 2021

[F1ExA.AS-30.D11.V1]

(Chapter 24)

REP11-075Heritage Assessment GIS Addendum1

Deadline 11

7 June 2021

[F1ExA.AS-30.D11.V1_01]

(Chapter 24)

REP11-076Heritage Assessment GIS Addendum App 1 CHVP2 App 24.7 Fig 7 Update1

Deadline 11

7 June 2021

[F1ExA.AS-30.D11.V1_02]

(Chapter 24)

REP11-077Heritage Assessment GIS Addendum App 2 CHVP3 App 24.7 Fig 8 Update1

Deadline 11

7 June 2021

[F1ExA.AS-30.D11.V1_03]

(Chapter 24)

REP11-078Heritage Assessment GIS Addendum App 3 CHVP4 App 24.7 Fig 9 Update1

Deadline 11

7 June 2021

ExA.AS-30.D11.V1_04 (Chapter 24)REP11-054Heritage Assessment GIS Addendum App 4 CHVP5 App 24.7 Fig 10 Update1

Deadline 11

7 June 2021

[F1ExA.AS-30.D11.V1_05]

(Chapter 24)

REP11-079Heritage Assessment GIS Addendum App 5 CHVP7 App 24.7 Fig 12 Update1

Deadline 11

7 June 2021

[F1ExA.AS-30.D11.V1_06]

(Chapter 24)

REP11-080Heritage Assessment GIS Addendum App 6 CHVP8 App 24.7 Fig 131

Deadline 11

7 June 2021

ExA.AS-14.D8.V1

(Chapter 25)

REP8-039

(APP-073)

Applicants’ Position Statement on Noise1

Deadline 8

25 March 2021

ExA.AS-8.D2.V1

(Chapter 25)

REP2-011

(APP-073)

Noise and Vibration Assessment Clarification Note1

Deadline 2

17 November 2020

ExA.AS-8.D4.V1

(Chapter 25)

REP4-043

(APP-073)

Noise Modelling Clarification Note1

Deadline 4

13 January 2021

ExA.WQ-1.A14.D1.V1

(Chapter 26)

REP1-103

(APP-074)

Applicants’ Responses to WQ1 Appendix 14 Junction Locations1

Deadline 1

2 November 2020

ExA.AS-8.D1.V1 (Chapter 26)

REP1-048

(APP-074)

Traffic and Transport Clarification Note for Deadline 11

Deadline 1

2 November 2020

ExA.AS-6.D6.V2

(Chapter 26)

REP6-043

(APP-074)

Sizewell C Cumulative Impact Assessment Note (Traffic and Transport)2

Deadline 6

24 February 2021

ExA.AS-9.D3.V1

(Chapter 26)

REP3-055

(APP-074)

Traffic and Transport Clarification Note for Deadline 31

Deadline 3

15 December 2020

ExA.AS-26.D4.V1

(Chapter 26)

REP4-027

(APP-074)

Traffic and Transport Deadline 4 Clarification Note1

Deadline 4

13 January 2021

ExA.AS-9.D1.V1

(Chapters 27 to 30)

REP1-049

(APP-075 to APP-078)

Public Rights of Way Clarification Note1

Deadline 1

2 November 2020

ExA.AS-5.D2.V1

(Chapter 28)

(Chapter 29)

REP2-008

(APP-076)

(APP-077)

Effects with Regard to the Statutory Purposes of the Suffolk Coast and Heaths Area of Outstanding Natural Beauty and Accordance with NPS Policy1

Deadline 2

17 November 2020

ExA.AS-33.D8.V1

(Chapter 28)

REP8-075

(APP-076)

Landscape and Visual: Sizewell C Cumulative Impact Assessment1

Deadline 8

25 March 2021

ExA.WQ-1.A9.1.D1.V1

(Chapter 29)

REP1-093

(APP-077)

Applicants’ Responses to WQ1 Appendix 9.1 EA1N Annotated Viewpoint 11

Deadline 1

2 November 2020

ExA.WQ-1.A9.2.D1.V1

(Chapter 29)

REP1-094

(APP-077)

Applicants’ Responses to WQ1 Appendix 9.2 EA1N Annotated Viewpoint 31

Deadline 1

2 November 2020

ExA.WQ-1.A9.3.D1.V1

(Chapter 29)

REP1-095

(APP-077)

Applicants’ Responses to WQ1 Appendix 9.3 EA1N Annotated Viewpoint 41

Deadline 1

2 November 2020

ExA.WQ-1.A9.4.D1.V1

(Chapter 29)

REP1-096

(APP-077)

Applicants’ Responses to WQ1 Appendix 9.4 EA1N Annotated Viewpoint 51

Deadline 1

2 November 2020

ExA.WQ-1.A9.5.D1.V1

(Chapter 29)

REP1-097

(APP-077)

Applicants’ Responses to WQ1 Appendix 9.5 EA1N Annotated Viewpoint 81

Deadline 1

2 November 2020

ExA.WQ-1.A9.6.D1.V1

(Chapter 29)

REP1-098

(APP-077)

Applicants’ Responses to WQ1 Appendix 9.6 EA1N Annotated Viewpoint 141

Deadline 1

2November 2020

ExA.AS-7.D2.V1

(Chapter 29)

REP2-010

(APP-077)

Sizewell C Cumulative Impact Assessment Note (Landscape and Visual)1

Deadline 2

17 November 2020

ExA.AS-3.D4.V1

(Chapter 29)

REP4-031

(APP-077)

Landscape and Visual Impact Assessment Addendum1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_001

(Chapter 29)

REP4-032

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 1 Viewpoint 1 – Public Right of Way (PRoW) near Friston House (Figure 29.13 Update)1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_002

(Chapter 29)

REP4-033

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 2 Viewpoint 2 – Friston, Church Road (Figure 29.14 Update)1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_003

(Chapter 29)

REP4-034

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 3 Viewpoint 3 – Grove Road, near Pear Tree Farm (Figure 29.15 Update)1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_004

(Chapter 29)

REP4-035

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 4 Viewpoint 4 – Grove Road, near Church Road (Friston) (Figure 29.16 Update)1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_005

(Chapter 29)

REP4-036

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 5 Viewpoint 5 – PRoW near Moor Farm (Figure 29.17 Update)1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_006

(Chapter 29)

REP4-037

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 6 Viewpoint 6 – Friston, Village Green (Figure 29.18 Update)1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_007

(Chapter 29)

REP4-038

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 7 Viewpoint 8 – Saxmundham Road (North of Friston) (Figure 29.20 Update)1

Deadline 4

13 January 2021

ExA.AS-3.D4.V1_008

(Chapter 29)

REP4-039

(APP-077)

Landscape and Visual Impact Assessment Addendum Appendix 8 Viewpoint 9 – B1121 Aldeburgh Road, south of Friston (Figure 29.21 Update)1

Deadline 4

13 January 2021

ExA.AS-6.D7.V1

(Chapter 29)

REP7-062

(APP-077)

Updated Figure 29.37- Viewpoint 5 Public Rights of Way, near Moor Farm (with National Grid GIS Substation)1

Deadline 7

4 March 2021

ExA.AS-28.D8.V1_01

(Chapter 29)

REP8-055

(APP-077)

National Grid GIS Substation Photomontages: Figure 29.13 Update Viewpoint 1 Public Rights of Way near Friston House1

Deadline 8

25 March 2021

ExA.AS-28.D8.V1_02

(Chapter 29)

REP8-056

(APP-077)

National Grid GIS Substation Photomontages: Figure 29.14 Update Viewpoint 2 Friston, Church Road1

Deadline 8

25 March 2021

ExA.AS-28.D8.V1_03

(Chapter 29)

REP8-057

(APP-077)

National Grid GIS Substation Photomontages: Figure 29.17 Update Viewpoint 5 Public Rights of Way, near Moor Farm1

Deadline 8

25 March 2021

ExA.AS-28.D8.V1_04

(Chapter 29)

REP8-058

(APP-077)

National Grid GIS Substation Photomontages: Figure 29.20 Update Viewpoint 8 Saxmundham Road (North of Friston)1

Deadline 8

25 March 2021

ExA.AS-28.D8.V1_05

(Chapter 29)

REP8-059

(APP-077)

National Grid GIS Substation Photomontages: Figure 29.21 Update Viewpoint 9: B1121 Aldeburgh Road (south of Friston)1

Deadline 8

25 March 2021

ExA.AS-28.D8.V1_06

(Chapter 29)

REP8-060

(APP-077)

National Grid GIS Substation Photomontages: CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8-Update)1

Deadline 8

25 March 2021

ExA.AS-28.D8.V1_07

(Chapter 29)

REP8-061

(APP-077)

National Grid GIS Substation Photomontages: CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9-Update)1

Deadline 8

25 March 2021

ExA.AS-28.D8.V1_08

(Chapter 29)

REP8-062

(APP-077)

National Grid GIS Substation Photomontages: CHVP5 – PRoW at Woodside Farm (Appendix 24.7, Figure 10-Update)1

Deadline 8

25 March 2021

ExA.AS-30.D8.V1_01

(Chapter 29)

REP8-066

(APP-077)

Different colour schemes for Substations Design Principles Statement: Viewpoint 1 Public Rights of Way near Friston House1

Deadline 8

25 March 2021

ExA.AS-30.D8.V1_02

(Chapter 29)

REP8-067

(APP-077)

Different colour schemes for Substations Design Principles Statement: Viewpoint 2 Friston, Church Road1

Deadline 8

25 March 2021

ExA.AS-30.D8.V1_03

(Chapter 29)

REP8-068

(APP-077)

Different colour schemes for Substations Design Principles Statement: Viewpoint 9 – B1121 Aldeburgh Road, south of Friston1

Deadline 8

25 March 2021

ExA.AS-31.D8.V1_01

(Chapter 29)

REP8-071

(APP-077)

Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.14 Update Viewpoint 2 Friston, Church Road1

Deadline 8

25 March 2021

ExA.AS-31.D8.V1_02

(Chapter 29)

REP8-072

(APP-077)

Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.17 Update Viewpoint 5 Public Rights of Way, near Moor Farm1

Deadline 8

25 March 2021

ExA.AS-31.D8.V1_03

(Chapter 29)

REP8-073

(APP-077)

Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.20 Update Viewpoint 8 Saxmundham Road (North of Friston)1

Deadline 8

25 March 2021

ExA.AS-31.D8.V1_04

(Chapter 29)

REP8-069

(APP-077)

Viewpoint Photomontages with Potential National Grid Extension Bays: CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8-Update)1

Deadline 8

25 March 2021

ExA.AS-31.D8.V1_05

(Chapter 29)

REP8-070

(APP-077)

Viewpoint Photomontages with Potential National Grid Extension Bays: CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9-Update)1

Deadline 8

25 March 2021

ExA.AS-32.D8.V1

(Chapter 29)

REP8-074

(APP-077)

Extension of National Grid Substation Appraisal1

Deadline 8

25 March 2021

ExA.AS-4.D11.V1

(Chapter 29)

REP11-028Landscape and Visual Impact Assessment GIS Addendum1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_01

(Chapter 29)

REP11-029LVIA GIS Addendum Appendix 1 Viewpoint 1 Figure 29.13 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_02

(Chapter 29)

REP11-030LVIA GIS Addendum Appendix 2 Viewpoint 2 Figure 29.14 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_03

(Chapter 29)

REP11-031LVIA GIS Addendum Appendix 3 Viewpoint 3 Figure 29.15 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_04

(Chapter 29)

REP11-032LVIA GIS Addendum Appendix 4 Viewpoint 4 Figure 29.16 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_05

(Chapter 29)

REP11-033LVIA GIS Addendum Appendix 5 Viewpoint 5 Figure 29.17 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_06

(Chapter 29)

REP11-034LVIA GIS Addendum Appendix 6 Viewpoint 6 Figure 29.18 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_07

(Chapter 29)

REP11-035LVIA GIS Addendum Appendix 7 Viewpoint 8 Figure 29.20 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_08

(Chapter 29)

REP11-036LVIA GIS Addendum Appendix 8 Viewpoint 9 Figure 29.21 GIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_09

(Chapter 29)

REP11-037LVIA GIS Addendum Appendix 9 Viewpoint 1 Figure 29.13 AIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_10

(Chapter 29)

REP11-038LVIA GIS Addendum Appendix 10 Viewpoint 2 Figure 29.14 AIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_11

(Chapter 29)

REP11-039LVIA GIS Addendum Appendix 11 Viewpoint 3 Figure 29.15 AIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_12

(Chapter 29)

REP11-040LVIA GIS Addendum Appendix 12 Viewpoint 4 Figure 29.16 AIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_13

(Chapter 29)

REP11-041LVIA GIS Addendum Appendix 13 Viewpoint 5 Figure 29.17 AIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_14

(Chapter 29)

REP11-042LVIA GIS Addendum Appendix 14 Viewpoint 6 Figure 29.18 AIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_15

(Chapter 29)

REP11-043LVIA GIS Addendum Appendix 15 Viewpoint 8 Figure 29.20 AIS Update1

Deadline 11

7 June 2021

ExA.AS-4.D11.V1_16

(Chapter 29)

REP11-044LVIA GIS Addendum Appendix 16 Viewpoint 9 Figure 29.21 AIS Update1

Deadline 11

7 June 2021

ExA.AS-17.D1.V1

(Chapter 30)

REP1-036

(APP-078)

Socio-Economics and Tourism Clarification Note (SZC CIA)1

Deadline 1

2 November 2020

ExA.WQ-1.A13.D1.V1

(Chapter 30)

REP1-102

(APP-078)

Applicants’ Responses to WQ1 Appendix 13 Tourism Impact Review1

Deadline 1

2 November 2020

5.3APP-043Habitat Regulations Assessment - Information to Support the Appropriate Assessment Report125 October 2019
5.3.1APP-044Habitat Regulations Assessment - Appendix 1 - Information to Support AA Report - HRA Screening Report125 October 2019
5.3.2REP3-016Habitat Regulations Assessment Appendix 2 – Information to Support AA Report – Screening Matrices3

Deadline 3

15 December 2020

5.3.3APP-046Habitat Regulations Assessment - Appendix 3 - Information to Support AA Report - Integrity Matrices125 October 2019

ExA.AS-19.D1.V1

(Chapter 11)

REP1-038

(APP-059)

Information to Support AA – Addendum for Marine Mammals1

Deadline 1

2 November 2020

[F3ExA.AS-7.D1.V1 (Information to Support Appropriate Assessment Report)

REP1-047

(APP-043 to APP-047)

Deadline 1 Offshore Ornithology Cumulative and In Combination Collision Risk Update 1

Deadline 1

2 November 2020]

ExA.AS-7.D4.V1

(Information to Support Appropriate Assessment Report)

REP4-042

(APP-043 to APP-047)

Deadline 4 Offshore Ornithology Cumulative and In Combination Collision Risk Update1

Deadline 4

13 January 2021

ExA.AS-11.D8.V1

(Information to Support Appropriate Assessment Report)

REP8-035

(APP-043 to APP-047)

Deadline 8 Offshore Ornithology Cumulative and In Combination Collision Risk Update1

Deadline 8

25 March 2021

ExA.AS-3.D11.V1

(Information to Support Appropriate Assessment Report)

REP11-027

(APP-043 to APP-047)

Deadline 11 Offshore Ornithology Cumulative and In Combination Collision Risk and Displacement Update1

Deadline 11

7 June 2021

[F3ExA.AS-8.D12.V1

(Information to Support Appropriate Assessment Report)

REP12-066 (APP-043 to APP-047) Deadline 12 Offshore Ornithology Cumulative and In Combination Collision Risk and Displacement Update1

Deadline 13

5 July 2021]

ExA.AS-12.D13.V1

(Information to Support Appropriate Assessment Report)

REP13-019

(APP-043 to APP-047)

Deadline 13 Offshore Ornithology Cumulative and In-Combination Collision Risk and Displacement Update1

Deadline 13

5 July 2021

[F3ExA.AS-3.SoSQ.V1

(Information to Support Appropriate Assessment Report)

(APP-043 to APP-047)

Updated Offshore Ornithology

Cumulative and In-Combination

Collision Risk and Displacement

Assessment

130 November 2021]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources