Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Commencement Information
I1Sch. 17 Pt. 1 in force at 22.4.2022, see art. 1(2)
(1) | (2) | (3) | (4) | (5) |
---|---|---|---|---|
Document Reference (and relevant ES Chapters) | Examination Library Reference (and relevant ES Chapter reference) | Document Name | Version | Date |
6.1 | APP-049 to APP-079 | Environmental Statement | 1 | 25 October 2019 |
6.2 | APP-080 to APP-441 | Figures | 1 | 25 October 2019 |
6.3 | APP-442 to APP-571 | Technical Appendices | 1 | 25 October 2019 |
ExA.WQ-1.A10.D1.V1 (Chapter 6) | REP1-099 (APP-054) | Applicants’ Responses to WQ1 Appendix 10 Landfall Indicative HDD Working Area | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A11.D1.V1 (Chapter 6) | REP1-100 (APP-054) | Applicants’ Responses to WQ1 Appendix 11 Landfall HDD Cross Sections | 1 | Deadline 1 2 November 2020 |
ExA.AS-13.D6.V1 (Chapter 6) | REP6-024 (APP-054) | HDD Verification Clarification Note | 1 | Deadline 6 24 February 2021 |
ExA.WQ-1.A6.D1.V1 (Chapter 6) | REP1-090 (APP-054) | Applicants’ Responses to WQ1 Appendix 6 Illustrative Open Trench and Trenchless Onshore Cable Route | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A7.D1.V1 (Chapter 6) | REP1-091 (APP-054) | Applicants’ Responses to WQ1 Appendix 7 Onshore Crossing Schedule | 1 | Deadline 1 2 November 2020 |
ExA.AS-10.D3.V1 (Chapter 6) | REP3-056 (APP-054) | Onshore Cable Route Works Programme Clarification Note | 1 | Deadline 3 15 December 2020 |
ExA.AS-11.D3.V1 (Chapter 6) (Chapter 29) | REP3-057 (APP-054) (APP-077) | Onshore Substations Update Clarification Note | 1 | Deadline 3 15 December 2020 |
ExA.AS-12.D3.V1 (Chapter 6) | REP3-058 (APP-054) | Construction in Proximity to Properties | 1 | Deadline 3 15 December 2020 |
6.3.6.2 (Chapter 6) | REP8-015 (APP-054) | EA1N Environmental Statement Appendix 6.2 Relationship of Onshore Plans Secured by the DCO | 5 | Deadline 8 25 March 2021 |
6.3.6.3 (Chapter 6) | REP8-016 (APP-054) | EA1N Environmental Statement Appendix 6.3 Relationship of Offshore Plans Secured by the DCO | 5 | Deadline 8 25 March 2021 |
6.3.6.4 (Chapter 6) | REP3-020 (APP-054) | EA1N Environmental Statement Appendix 6.4 Cumulative Project Description | 2 | Deadline 3 15 December 2020 |
ExA.RRA6.D0.V1 (Chapters 7 to 17) | AS-043 (APP-055 to APP-065) | [F1Applicant’s Comments on Relevant Representations] F2... Appendix 6 Disposal Site Locations (Windfarm Site) | 1 | 11 June 2020 |
ExA.RRA2.D0.V1 (Chapter 7) | AS-039 (APP-055) | [F1Applicant’s Comments on Relevant Representations] F2... Appendix 2 Wave Climatology Clarification Note | 1 | 11 June 2020 |
ExA.AS-13.D3.V1 (Chapter 7) (Chapter 9) (Chapter 10) (Chapter 12) | REP3-059 (APP-055) (APP-057) (APP-058) (APP-060) | Effects on Supporting Habitats of Outer Thames Estuary SPA Clarification Note | 1 | Deadline 3 15 December 2020 |
ExA.RRA3.D0.V1 (Chapter 10) | AS-040 (APP-058) | [F1Applicant’s Comments on Relevant Representations] F2... Appendix 3 Fish and Shellfish Ecology Clarification Note | 1 | 11 June 2020 |
ExA.AS-5.D11.V2 (Chapter 11) | REP11-045 [F1(APP-059)] | Underwater Noise Modelling [F3Report Update] Update | 2 | Deadline 11 7 June 2021 |
ExA.AS-3.D2.V1 (Chapter 12) | REP2-006 (APP-060) | Cumulative Auk Displacement [F4and], Seabird Assemblage Assessment of FFC SPA and Gannet PVA | 1 | Deadline 2 17 November 2020 |
ExA.AS-2.D11.V5 (Chapter 12) | REP11-026 (APP-060) | Displacement of red-throated divers in the Outer Thames Estuary SPA | 5 | Deadline 11 7 June 2021 |
ExA.AS-20.D1.V1 (Chapter 19) (Chapter 26) | REP1-040 (APP-067) (APP-074) | Deadline 1 Air Quality Clarification Note | 1 | Deadline 1 2 November 2020 |
ExA.AS-16.D3.V1 (Chapter 19) | REP3-061 (APP-067) | Deadline 3 Air Quality Clarification Note | 1 | Deadline 3 15 December 2020 |
ExA.WQ-1.A8.D1.V1 (Chapter 20) | REP1-092 (APP-068) | Applicants’ Responses to WQ1 Appendix 8 Environment Agency Flood Zones | 1 | Deadline 1 2 November 2020 |
ExA.AS-9.D4.V2 (Chapter 20) | REP4-044 (APP-068) | [F3Clarification Note] SuDS Infiltration Note | 2 | Deadline 4 13 January 2021 |
ExA.AS-12.D6.V1 (Chapter 18)(Chapter 20) | REP6-021 (APP-066) (APP-068) | Landfall Hydrogeological Risk Assessment | 1 | Deadline 6 24 February 2021 |
ExA.AS-13.D8.V1 (Chapter 20) | REP8-038 (APP-068) | Flood Risk and Drainage Clarification Note | 1 | Deadline 8 25 March 2021 |
ExA.AS-11.D1.V1 (Chapter 21) | REP1-022 (APP-069) | Land Use Clarification Note | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A4.D1.V1 (Chapter 22) | REP1-088 (APP-070) | Applicants’ Responses to WQ1 Appendix 4 Ecological Mitigation Works | 1 | Deadline 1 2 November 2020 |
ExA.AS-12.D1.V1 (Chapter 22) | REP1-023 (APP-070) | Onshore Ecology Clarification Note | 1 | Deadline 1 2 November 2020 |
ExA.AS-16.D1.V1 (Chapter 22) | REP1-035 (APP-070) | Ecological Enhancement Clarification Note | 1 | Deadline 1 2 November 2020 |
ExA.AS-14.D3.V1 (Chapter 22) | REP3-060 (APP-070) | Deadline 3 Onshore Ecology Clarification Note | 1 | Deadline 3 15 December 2020 |
ExA.AS-10.D4.V1 (Chapter 22) | REP4-005 (APP-070) | Deadline 4 Onshore Ecology Clarification Note | 1 | Deadline 4 13 January 2021 |
ExA.AS-14.D6.V1 (Chapter 22) | REP6-025 (APP-070) | Deadline 6 Onshore Ecology Clarification Note | 1 | Deadline 6 24 February 2021 |
ExA.AS-28.D6.V1 (Chapter 22) | REP6-035 (APP-070) | Ecology Survey Results: February 2021 | 1 | Deadline 6 24 February 2021 |
ExA.AS-16.D8.V1 (Chapter 22) | REP8-041 (APP-070) | Ecological Enhancement Clarification Note Addendum | 1 | Deadline 8 25 March 2021 |
ExA.AS-10.D1.V1 (Chapter 24) (Chapter 29) | REP1-021 (APP-072) (APP-077) | Archaeology and Cultural Heritage Clarification Note | 1 | Deadline 1 2 November 2020 |
ExA.AS-13.D1.V1 (Chapter 24) | REP1-024 (APP-072) | Pre-Construction Trial Trenching Report | 1 | Deadline 1 2 November 2020 |
ExA.AS-14.D1.V1 (Chapter 24) | REP1-025 to REP1-033 (APP-072) | Onshore Archaeology Geophysical Survey Report (Parts 1 to 9) | 1 | Deadline 1 2 November 2020 |
ExA.AS-15.D1.V1 (Chapter 24) | REP1-034 (APP-072) | Onshore Archaeology Earthworks Report | 1 | Deadline 1 2 November 2020 |
ExA.AS-29.D8.V1 (Chapter 24) | REP8-063 (APP-072) | Cultural heritage Viewpoint 5 Additional Visualisation | 1 | Deadline 8 25 March 2021 |
ExA.AS-16.D3.V1 (Chapter 24) (Chapter 29) | REP3-062 to REP3-068 (APP-072) (APP-077) | Updated Photomontages Clarification Note | 1 | Deadline 3 15 December 2020 |
ExA.AS-11.D4.V1 (Chapter 24) | REP4-006 (APP-072) | Heritage Assessment Addendum | 1 | Deadline 4 13 January 2021 |
ExA.AS-11.D4.V1_001 (Chapter 24) | REP4-007 (APP-072) | Heritage Assessment Addendum Appendix 1 CHVP2 –PRoW between Friston Hall and Friston (Appendix 24.7, Figure 7 Update) | [F51] | Deadline 4 13 January 2021 |
ExA.AS-11.D4.V1_002 (Chapter 24) | REP4-008 (APP-072) | Heritage Assessment Addendum Appendix 2 CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8 Update) | [F51] | Deadline 4 13 January 2021 |
ExA.AS-11.D4.V1_003 (Chapter 24) | REP4-009 (APP-072) | Heritage Assessment Addendum Appendix 3 CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9 Update) | [F51] | Deadline 4 13 January 2021 |
ExA.AS-11.D4.V1_004 (Chapter 24) | REP4-010 (APP-072) | Heritage Assessment Addendum Appendix 4 CHVP5 – PRoW at Woodside Farm (Appendix 24.7, Figure 10 Update) | [F51] | Deadline 4 13 January 2021 |
ExA.AS-11.D4.V1_005 (Chapter 24) | REP4-011 (APP-072) | Heritage Assessment Addendum Appendix 5 CHVP7 – Friston House (b) (Appendix 24.7, Figure 12 Update) | [F51] | Deadline 4 13 January 2021 |
ExA.AS-11.D4.V1_006 (Chapter 24) | REP4-012 (APP-072) | Heritage Assessment Addendum Appendix 6 CHVP8 – Friston War Memorial (Appendix 24.7, Figure 13 Update) | [F51] | Deadline 4 13 January 2021 |
[F1ExA.AS-30.D11.V1] (Chapter 24) | REP11-075 | Heritage Assessment GIS Addendum | 1 | Deadline 11 7 June 2021 |
[F1ExA.AS-30.D11.V1_01] (Chapter 24) | REP11-076 | Heritage Assessment GIS Addendum App 1 CHVP2 App 24.7 Fig 7 Update | 1 | Deadline 11 7 June 2021 |
[F1ExA.AS-30.D11.V1_02] (Chapter 24) | REP11-077 | Heritage Assessment GIS Addendum App 2 CHVP3 App 24.7 Fig 8 Update | 1 | Deadline 11 7 June 2021 |
[F1ExA.AS-30.D11.V1_03] (Chapter 24) | REP11-078 | Heritage Assessment GIS Addendum App 3 CHVP4 App 24.7 Fig 9 Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-30.D11.V1_04 (Chapter 24) | REP11-054 | Heritage Assessment GIS Addendum App 4 CHVP5 App 24.7 Fig 10 Update | 1 | Deadline 11 7 June 2021 |
[F1ExA.AS-30.D11.V1_05] (Chapter 24) | REP11-079 | Heritage Assessment GIS Addendum App 5 CHVP7 App 24.7 Fig 12 Update | 1 | Deadline 11 7 June 2021 |
[F1ExA.AS-30.D11.V1_06] (Chapter 24) | REP11-080 | Heritage Assessment GIS Addendum App 6 CHVP8 App 24.7 Fig 13 | 1 | Deadline 11 7 June 2021 |
ExA.AS-14.D8.V1 (Chapter 25) | REP8-039 (APP-073) | Applicants’ Position Statement on Noise | 1 | Deadline 8 25 March 2021 |
ExA.AS-8.D2.V1 (Chapter 25) | REP2-011 (APP-073) | Noise and Vibration Assessment Clarification Note | 1 | Deadline 2 17 November 2020 |
ExA.AS-8.D4.V1 (Chapter 25) | REP4-043 (APP-073) | Noise Modelling Clarification Note | 1 | Deadline 4 13 January 2021 |
ExA.WQ-1.A14.D1.V1 (Chapter 26) | REP1-103 (APP-074) | Applicants’ Responses to WQ1 Appendix 14 Junction Locations | 1 | Deadline 1 2 November 2020 |
ExA.AS-8.D1.V1 (Chapter 26) | REP1-048 (APP-074) | Traffic and Transport Clarification Note for Deadline 1 | 1 | Deadline 1 2 November 2020 |
ExA.AS-6.D6.V2 (Chapter 26) | REP6-043 (APP-074) | Sizewell C Cumulative Impact Assessment Note (Traffic and Transport) | 2 | Deadline 6 24 February 2021 |
ExA.AS-9.D3.V1 (Chapter 26) | REP3-055 (APP-074) | Traffic and Transport Clarification Note for Deadline 3 | 1 | Deadline 3 15 December 2020 |
ExA.AS-26.D4.V1 (Chapter 26) | REP4-027 (APP-074) | Traffic and Transport Deadline 4 Clarification Note | 1 | Deadline 4 13 January 2021 |
ExA.AS-9.D1.V1 (Chapters 27 to 30) | REP1-049 (APP-075 to APP-078) | Public Rights of Way Clarification Note | 1 | Deadline 1 2 November 2020 |
ExA.AS-5.D2.V1 (Chapter 28) (Chapter 29) | REP2-008 (APP-076) (APP-077) | Effects with Regard to the Statutory Purposes of the Suffolk Coast and Heaths Area of Outstanding Natural Beauty and Accordance with NPS Policy | 1 | Deadline 2 17 November 2020 |
ExA.AS-33.D8.V1 (Chapter 28) | REP8-075 (APP-076) | Landscape and Visual: Sizewell C Cumulative Impact Assessment | 1 | Deadline 8 25 March 2021 |
ExA.WQ-1.A9.1.D1.V1 (Chapter 29) | REP1-093 (APP-077) | Applicants’ Responses to WQ1 Appendix 9.1 EA1N Annotated Viewpoint 1 | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A9.2.D1.V1 (Chapter 29) | REP1-094 (APP-077) | Applicants’ Responses to WQ1 Appendix 9.2 EA1N Annotated Viewpoint 3 | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A9.3.D1.V1 (Chapter 29) | REP1-095 (APP-077) | Applicants’ Responses to WQ1 Appendix 9.3 EA1N Annotated Viewpoint 4 | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A9.4.D1.V1 (Chapter 29) | REP1-096 (APP-077) | Applicants’ Responses to WQ1 Appendix 9.4 EA1N Annotated Viewpoint 5 | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A9.5.D1.V1 (Chapter 29) | REP1-097 (APP-077) | Applicants’ Responses to WQ1 Appendix 9.5 EA1N Annotated Viewpoint 8 | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A9.6.D1.V1 (Chapter 29) | REP1-098 (APP-077) | Applicants’ Responses to WQ1 Appendix 9.6 EA1N Annotated Viewpoint 14 | 1 | Deadline 1 2November 2020 |
ExA.AS-7.D2.V1 (Chapter 29) | REP2-010 (APP-077) | Sizewell C Cumulative Impact Assessment Note (Landscape and Visual) | 1 | Deadline 2 17 November 2020 |
ExA.AS-3.D4.V1 (Chapter 29) | REP4-031 (APP-077) | Landscape and Visual Impact Assessment Addendum | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_001 (Chapter 29) | REP4-032 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 1 Viewpoint 1 – Public Right of Way (PRoW) near Friston House (Figure 29.13 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_002 (Chapter 29) | REP4-033 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 2 Viewpoint 2 – Friston, Church Road (Figure 29.14 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_003 (Chapter 29) | REP4-034 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 3 Viewpoint 3 – Grove Road, near Pear Tree Farm (Figure 29.15 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_004 (Chapter 29) | REP4-035 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 4 Viewpoint 4 – Grove Road, near Church Road (Friston) (Figure 29.16 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_005 (Chapter 29) | REP4-036 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 5 Viewpoint 5 – PRoW near Moor Farm (Figure 29.17 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_006 (Chapter 29) | REP4-037 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 6 Viewpoint 6 – Friston, Village Green (Figure 29.18 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_007 (Chapter 29) | REP4-038 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 7 Viewpoint 8 – Saxmundham Road (North of Friston) (Figure 29.20 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-3.D4.V1_008 (Chapter 29) | REP4-039 (APP-077) | Landscape and Visual Impact Assessment Addendum Appendix 8 Viewpoint 9 – B1121 Aldeburgh Road, south of Friston (Figure 29.21 Update) | 1 | Deadline 4 13 January 2021 |
ExA.AS-6.D7.V1 (Chapter 29) | REP7-062 (APP-077) | Updated Figure 29.37- Viewpoint 5 Public Rights of Way, near Moor Farm (with National Grid GIS Substation) | 1 | Deadline 7 4 March 2021 |
ExA.AS-28.D8.V1_01 (Chapter 29) | REP8-055 (APP-077) | National Grid GIS Substation Photomontages: Figure 29.13 Update Viewpoint 1 Public Rights of Way near Friston House | 1 | Deadline 8 25 March 2021 |
ExA.AS-28.D8.V1_02 (Chapter 29) | REP8-056 (APP-077) | National Grid GIS Substation Photomontages: Figure 29.14 Update Viewpoint 2 Friston, Church Road | 1 | Deadline 8 25 March 2021 |
ExA.AS-28.D8.V1_03 (Chapter 29) | REP8-057 (APP-077) | National Grid GIS Substation Photomontages: Figure 29.17 Update Viewpoint 5 Public Rights of Way, near Moor Farm | 1 | Deadline 8 25 March 2021 |
ExA.AS-28.D8.V1_04 (Chapter 29) | REP8-058 (APP-077) | National Grid GIS Substation Photomontages: Figure 29.20 Update Viewpoint 8 Saxmundham Road (North of Friston) | 1 | Deadline 8 25 March 2021 |
ExA.AS-28.D8.V1_05 (Chapter 29) | REP8-059 (APP-077) | National Grid GIS Substation Photomontages: Figure 29.21 Update Viewpoint 9: B1121 Aldeburgh Road (south of Friston) | 1 | Deadline 8 25 March 2021 |
ExA.AS-28.D8.V1_06 (Chapter 29) | REP8-060 (APP-077) | National Grid GIS Substation Photomontages: CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8-Update) | 1 | Deadline 8 25 March 2021 |
ExA.AS-28.D8.V1_07 (Chapter 29) | REP8-061 (APP-077) | National Grid GIS Substation Photomontages: CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9-Update) | 1 | Deadline 8 25 March 2021 |
ExA.AS-28.D8.V1_08 (Chapter 29) | REP8-062 (APP-077) | National Grid GIS Substation Photomontages: CHVP5 – PRoW at Woodside Farm (Appendix 24.7, Figure 10-Update) | 1 | Deadline 8 25 March 2021 |
ExA.AS-30.D8.V1_01 (Chapter 29) | REP8-066 (APP-077) | Different colour schemes for Substations Design Principles Statement: Viewpoint 1 Public Rights of Way near Friston House | 1 | Deadline 8 25 March 2021 |
ExA.AS-30.D8.V1_02 (Chapter 29) | REP8-067 (APP-077) | Different colour schemes for Substations Design Principles Statement: Viewpoint 2 Friston, Church Road | 1 | Deadline 8 25 March 2021 |
ExA.AS-30.D8.V1_03 (Chapter 29) | REP8-068 (APP-077) | Different colour schemes for Substations Design Principles Statement: Viewpoint 9 – B1121 Aldeburgh Road, south of Friston | 1 | Deadline 8 25 March 2021 |
ExA.AS-31.D8.V1_01 (Chapter 29) | REP8-071 (APP-077) | Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.14 Update Viewpoint 2 Friston, Church Road | 1 | Deadline 8 25 March 2021 |
ExA.AS-31.D8.V1_02 (Chapter 29) | REP8-072 (APP-077) | Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.17 Update Viewpoint 5 Public Rights of Way, near Moor Farm | 1 | Deadline 8 25 March 2021 |
ExA.AS-31.D8.V1_03 (Chapter 29) | REP8-073 (APP-077) | Viewpoint Photomontages with Potential National Grid Extension Bays: Figure 29.20 Update Viewpoint 8 Saxmundham Road (North of Friston) | 1 | Deadline 8 25 March 2021 |
ExA.AS-31.D8.V1_04 (Chapter 29) | REP8-069 (APP-077) | Viewpoint Photomontages with Potential National Grid Extension Bays: CHVP3 – PRoW between Moor Farm and Little Moor Farm (Appendix 24.7, Figure 8-Update) | 1 | Deadline 8 25 March 2021 |
ExA.AS-31.D8.V1_05 (Chapter 29) | REP8-070 (APP-077) | Viewpoint Photomontages with Potential National Grid Extension Bays: CHVP4 – PRoW to east of Little Moor Farm (Appendix 24.7, Figure 9-Update) | 1 | Deadline 8 25 March 2021 |
ExA.AS-32.D8.V1 (Chapter 29) | REP8-074 (APP-077) | Extension of National Grid Substation Appraisal | 1 | Deadline 8 25 March 2021 |
ExA.AS-4.D11.V1 (Chapter 29) | REP11-028 | Landscape and Visual Impact Assessment GIS Addendum | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_01 (Chapter 29) | REP11-029 | LVIA GIS Addendum Appendix 1 Viewpoint 1 Figure 29.13 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_02 (Chapter 29) | REP11-030 | LVIA GIS Addendum Appendix 2 Viewpoint 2 Figure 29.14 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_03 (Chapter 29) | REP11-031 | LVIA GIS Addendum Appendix 3 Viewpoint 3 Figure 29.15 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_04 (Chapter 29) | REP11-032 | LVIA GIS Addendum Appendix 4 Viewpoint 4 Figure 29.16 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_05 (Chapter 29) | REP11-033 | LVIA GIS Addendum Appendix 5 Viewpoint 5 Figure 29.17 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_06 (Chapter 29) | REP11-034 | LVIA GIS Addendum Appendix 6 Viewpoint 6 Figure 29.18 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_07 (Chapter 29) | REP11-035 | LVIA GIS Addendum Appendix 7 Viewpoint 8 Figure 29.20 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_08 (Chapter 29) | REP11-036 | LVIA GIS Addendum Appendix 8 Viewpoint 9 Figure 29.21 GIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_09 (Chapter 29) | REP11-037 | LVIA GIS Addendum Appendix 9 Viewpoint 1 Figure 29.13 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_10 (Chapter 29) | REP11-038 | LVIA GIS Addendum Appendix 10 Viewpoint 2 Figure 29.14 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_11 (Chapter 29) | REP11-039 | LVIA GIS Addendum Appendix 11 Viewpoint 3 Figure 29.15 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_12 (Chapter 29) | REP11-040 | LVIA GIS Addendum Appendix 12 Viewpoint 4 Figure 29.16 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_13 (Chapter 29) | REP11-041 | LVIA GIS Addendum Appendix 13 Viewpoint 5 Figure 29.17 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_14 (Chapter 29) | REP11-042 | LVIA GIS Addendum Appendix 14 Viewpoint 6 Figure 29.18 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_15 (Chapter 29) | REP11-043 | LVIA GIS Addendum Appendix 15 Viewpoint 8 Figure 29.20 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-4.D11.V1_16 (Chapter 29) | REP11-044 | LVIA GIS Addendum Appendix 16 Viewpoint 9 Figure 29.21 AIS Update | 1 | Deadline 11 7 June 2021 |
ExA.AS-17.D1.V1 (Chapter 30) | REP1-036 (APP-078) | Socio-Economics and Tourism Clarification Note (SZC CIA) | 1 | Deadline 1 2 November 2020 |
ExA.WQ-1.A13.D1.V1 (Chapter 30) | REP1-102 (APP-078) | Applicants’ Responses to WQ1 Appendix 13 Tourism Impact Review | 1 | Deadline 1 2 November 2020 |
5.3 | APP-043 | Habitat Regulations Assessment - Information to Support the Appropriate Assessment Report | 1 | 25 October 2019 |
5.3.1 | APP-044 | Habitat Regulations Assessment - Appendix 1 - Information to Support AA Report - HRA Screening Report | 1 | 25 October 2019 |
5.3.2 | REP3-016 | Habitat Regulations Assessment Appendix 2 – Information to Support AA Report – Screening Matrices | 3 | Deadline 3 15 December 2020 |
5.3.3 | APP-046 | Habitat Regulations Assessment - Appendix 3 - Information to Support AA Report - Integrity Matrices | 1 | 25 October 2019 |
ExA.AS-19.D1.V1 (Chapter 11) | REP1-038 (APP-059) | Information to Support AA – Addendum for Marine Mammals | 1 | Deadline 1 2 November 2020 |
[F3ExA.AS-7.D1.V1 (Information to Support Appropriate Assessment Report) | REP1-047 (APP-043 to APP-047) | Deadline 1 Offshore Ornithology Cumulative and In Combination Collision Risk Update | 1 | Deadline 1 2 November 2020] |
ExA.AS-7.D4.V1 (Information to Support Appropriate Assessment Report) | REP4-042 (APP-043 to APP-047) | Deadline 4 Offshore Ornithology Cumulative and In Combination Collision Risk Update | 1 | Deadline 4 13 January 2021 |
ExA.AS-11.D8.V1 (Information to Support Appropriate Assessment Report) | REP8-035 (APP-043 to APP-047) | Deadline 8 Offshore Ornithology Cumulative and In Combination Collision Risk Update | 1 | Deadline 8 25 March 2021 |
ExA.AS-3.D11.V1 (Information to Support Appropriate Assessment Report) | REP11-027 (APP-043 to APP-047) | Deadline 11 Offshore Ornithology Cumulative and In Combination Collision Risk and Displacement Update | 1 | Deadline 11 7 June 2021 |
[F3ExA.AS-8.D12.V1 (Information to Support Appropriate Assessment Report) | REP12-066 (APP-043 to APP-047) | Deadline 12 Offshore Ornithology Cumulative and In Combination Collision Risk and Displacement Update | 1 | Deadline 13 5 July 2021] |
ExA.AS-12.D13.V1 (Information to Support Appropriate Assessment Report) | REP13-019 (APP-043 to APP-047) | Deadline 13 Offshore Ornithology Cumulative and In-Combination Collision Risk and Displacement Update | 1 | Deadline 13 5 July 2021 |
[F3ExA.AS-3.SoSQ.V1 (Information to Support Appropriate Assessment Report) | (APP-043 to APP-047) | Updated Offshore Ornithology Cumulative and In-Combination Collision Risk and Displacement Assessment | 1 | 30 November 2021] |
Textual Amendments
F1Words in Sch. 17 Pt. 1 substituted (22.12.2022) by The East Anglia ONE North Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1398), art. 1(2), Sch.
F2Word in Sch. 17 Pt. 1 omitted (22.12.2022) by virtue of The East Anglia ONE North Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1398), art. 1(2), Sch.
F3Words in Sch. 17 Pt. 1 inserted (22.12.2022) by The East Anglia ONE North Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1398), art. 1(2), Sch.
F4Word in Sch. 17 Pt. 1 inserted (22.12.2022) by The East Anglia ONE North Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1398), art. 1(2), Sch.
F5Word in Sch. 17 Pt. 1 substituted (22.12.2022) by The East Anglia ONE North Offshore Wind Farm (Correction) Order 2022 (S.I. 2022/1398), art. 1(2), Sch.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: