The Wrexham Gas Fired Generating Station Order 2017

Construction hours

11.—(1) Construction work for the authorised development must not take place outside the hours of—

(a)07:00 to 19:00 on Monday to Friday; and

(b)07:00 to 13:00 on Saturdays and public holidays.

(2) Sub-paragraph (1) does not prevent construction works being carried out on any Sunday or outside the hours set out in sub-paragraph (1) with the prior written approval of the relevant planning authority.