Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
6.35.—(1) This rule sets out the period for—
(a)filing an acknowledgment of service;
(b)filing an admission; or
(c)filing a defence,
where a claim form has been served out of the jurisdiction under rule 6.32 or 6.33.
(Part 10 contains rules about acknowledgments of service, Part 14 contains rules about admissions and Part 15 contains rules about defences.)
(2) Where the claimant serves on a defendant in Scotland or Northern Ireland under rule 6.32, the period—
(a)for filing an acknowledgment of service or admission is 21 days after service of the particulars of claim; or
(b)for filing a defence is—
(i)21 days after service of the particulars of claim; or
(ii)where the defendant files an acknowledgment of service, 35 days after service of the particulars of claim.
(Part 7 provides that particulars of claim must be contained in or served with the claim form or served separately on the defendant within 14 days after service of the claim form.)
F2(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F3(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(5) Where the claimant serves the claim form under rule 6.33 F4..., the period for responding to the claim form is set out in [F5Practice Direction 6B].]
Textual Amendments
F1Pt. 6 substituted (1.10.2008) by The Civil Procedure (Amendment) Rules 2008 (S.I. 2008/2178), rule 1(2), Sch. 1
F2Rule 6.35(3) omitted (31.12.2020) by virtue of The Civil Procedure Rules 1998 (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/521), regs. 1(1), 4(17)(a) (with reg. 18) (as amended by S.I. 2020/1493, regs. 1(1), 9(2)(b)(3)); 2020 c. 1, Sch. 5 para. 1(1)
F3Rule 6.35(4) omitted (31.12.2020) by virtue of The Civil Procedure Rules 1998 (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/521), regs. 1(1), 4(17)(a) (with reg. 18) (as amended by S.I. 2020/1493, regs. 1(1), 9(2)(b)(3)); 2020 c. 1, Sch. 5 para. 1(1)
F4Words in rule 6.35(5) omitted (31.12.2020) by virtue of The Civil Procedure Rules 1998 (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/521), regs. 1(1), 4(17)(b) (with reg. 18) (as amended by S.I. 2020/1493, regs. 1(1), 9(2)(b)(3)); 2020 c. 1, Sch. 5 para. 1(1)
F5Words in rule 6.35(5) substituted (6.4.2010) by The Civil Procedure (Amendment No.2) Rules 2009 (S.I. 2009/3390), rules 1(2), 5(g)(i)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.