Changes to legislation:

There are currently no known outstanding effects for the The Civil Procedure Rules 1998, Cross Heading: SECTION III. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

[F1[F2SECTION IIIE+W ENVIRONMENTAL REVIEW UNDER THE ENVIRONMENT ACT 2021

Scope and interpretationE+W

54.25(1) This Section contains rules about environmental review.

(2) In this Section—

(a)claim for environmental review” means a claim made by the Office for Environmental Protection (“OEP”) under section 38 of the Environment Act 2021;

(b)the environmental review procedure” means the Part 8 procedure as modified by this Section;

(c)interested party” means any person (other than the claimant and defendant) who is directly affected by the claim; and

(d)court” means the High Court.

Who may exercise the powers of the High CourtE+W

54.26(1) Rule 54.1A (excluding paragraph (3)(a) of the rule) applies to a claim for environmental review.

(2) A claim for environmental review shall be assigned to the Planning Court.

When this Section must be usedE+W

54.27(1) The environmental review procedure must be used where a claim for environmental review is made.

(2) Practice Direction 54E applies to the environmental review procedure.

Time limit for filing claim formE+W

54.28.(1) The claim form must be filed not later than 6 months from the date by which a response to a decision notice was required under section 36(3) of the Environment Act 2021.

(2) The time limit in paragraph (1) may be extended, but only upon application to the court by the claimant and if the court is satisfied that it is reasonable to do so.

Claim formE+W

54.29.(1) In addition to the matters set out in rule 8.2 (contents of the claim form) the claimant must also state—

(a)the name of the public authority, the defendant, against whom the claim for environmental review is brought;

(b)the name and address of any person the claimant considers to be an interested party; and

(c)any remedy (including any interim remedy) sought by the claimant.

(2) The claim form must be accompanied by the documents required by Practice Direction 54E.

Service of claim formE+W

54.30.  The claim form must be served on—

(a)the defendant; and

(b)unless the court otherwise directs, any person the claimant considers to be an interested party,

within 7 days after the date of issue.

Acknowledgment of serviceE+W

54.31.(1) Any person served with the claim form who wishes to take part in the environmental review must file an acknowledgment of service in the relevant practice form in accordance with the following provisions of this rule.

(2) Any acknowledgment of service must be—

(a)filed not more than 35 days after service of the claim form; and

(b)served on—

(i)the claimant; and

(ii)subject to any direction under rule 54.30(b), any other person named in the claim form,

as soon as practicable and, in any event, not later than 7 days after it is filed.

(3) The time limits under this rule may not be extended by agreement between the parties.

(4) The acknowledgment of service—

(a)must state the name and address of any person the person filing it considers to be an interested party; and

(b)may include or be accompanied by an application for directions.

(5) Rule 10.3(2) does not apply.

Detailed grounds and evidenceE+W

54.32.(1) A defendant and any other person served with the claim form who wishes to contest the claim or support it on additional grounds must file and serve with the acknowledgement of service—

(a)detailed grounds for contesting the claim or supporting it on additional grounds; and

(b)any written evidence.

F3(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F4(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Failure to file acknowledgment of serviceE+W

54.33.(1) Where a person served with the claim form has failed to file an acknowledgment of service in accordance with rule 54.31 or to comply with 54.32, they may not take part in the hearing of the claim unless the court allows them to do so and they comply with rule 54.31 or any other direction of the court regarding the filing and service of—

(a)detailed grounds for contesting the claim or supporting it on additional grounds; and

(b)any written evidence.

(2) Where that person takes part in the hearing of the environmental review, the court may take their failure to file an acknowledgment of service into account when deciding whether an order as to costs should be made.

(3) Rule 8.4 does not apply.

Where claimant seeks to rely on additional groundsE+W

54.34.  The court’s permission is required if the claimant seeks to rely on grounds other than those set out in the original claim.

Other procedural rulesE+W

54.35.  Rules 54.10 and 54.16 – 54.20 shall apply to the environmental review procedure, except that—

(a)references to “permission to proceed” shall be disregarded; and

(b)the reference in rule 54.19 to “the decision to which the claim relates” shall be read as referring to “the matter to which the claim relates.]]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules as a PDF

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.