xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

Prospective

SCHEDULE 3E+WOther contractual terms

PART 1E+WProvision of services

Premises, facilities and equipment E+W

1.—(1) The contractor must ensure that the premises used for the provision of services under the contract—

(a)are suitable for the delivery of those services,

(b)are sufficient to meet the reasonable needs of the contractor’s patients, and

(c)meet or exceed the minimum standards set out in directions issued by the Welsh Ministers under the Act.

(2) The requirement in sub-paragraph (1) is subject to any plan included in the contract in accordance with regulation 18(5) which sets out steps to be taken by the contractor to bring the premises up to the required standard.

(3) In relation to each service it provides, the contractor must provide such facilities and equipment as are necessary to enable it properly to perform that service.

Commencement Information

I1Sch. 3 para. 1 in force at 1.10.2023, see reg. 1(2)