SCHEDULEConditions
PART 1Conditions of building operations
Visual impact9
1
Building roofs must be finished in one of the following colours—
a
S 3005-Y20R;
b
S 3005-R80B;
c
S 7010-Y90R;
d
S 3502-R;
e
S 3005-G50Y.
2
Building facades, security fencing and acoustic barrier fencing must be finished in natural wood or in one of the following colours—
a
S 2040-G40Y;
b
S 2005-B20G;
c
S 3005-Y20R.
3
Other external elements must be finished in one of the following colours—
a
S 2040-G40Y;
b
S 2005-B20G;
c
S 3005-Y20R;
d
S 1515-Y90R;
e
S 0575-G90Y.
4
In this paragraph, “colours” refers to the colour that corresponds with the listed code on the Natural Colour System®.
5
In sub-paragraph (3), “other external elements” includes—
a
window frames;
b
trims;
c
architectural features;
d
ancillary structures;
e
handrails;
f
lighting columns;
g
exterior furniture such as benches.
6
In sub-paragraph (3), “other external elements” excludes solar photovoltaics or solar thermal equipment.
7
If any of the colours specified in this paragraph are not available for use at the relevant time, the developer may apply to the local authority for a relevant approval to use a closely matching colour.