PART 2Works Provisions

Principal powers

Power to deviate4.

In constructing or maintaining the onshore works the undertaker —

(a)

may in relation to Works Nos 3 to 9 deviate laterally to any extent from the lines or situations shown on the onshore plans within the limits of deviation;

(b)

must not in relation to Works Nos. 7 and 8 construct any works within 1.6 metres of the surface of the ground; and

(c)

may in relation to each of the authorised works specified in column (3) of the table set out in Chapter 2 of Part 2 to Schedule 1 to this Order, construct those works in the land identified in relation to that particular works in columns (1) and (2) of that table.