3.—(1) Subject to the provisions of this Order the undertaker may construct, maintain and decommission the authorised works.
(2) Subject to the provisions of this Order the undertaker may construct, maintain and decommission the tidal works or any parts thereof within the offshore Order limits.
(3) Subject to the provisions of this Order the undertaker may repower Work No. 1 or any parts thereof within the offshore Order limits.
(4) In constructing, maintaining, repowering and decommissioning the tidal works the documents in column 1 of Part 4 of Schedule 1 must be submitted to and approved in writing by the Welsh Ministers prior to the activity in column 2 occurring and such documents shall accord with any conditions relating to their content imposed on any marine licence for the relevant tidal works and shall not authorise any works outside the project parameters.
(5) The Welsh Ministers shall not approve any device deployment protocol pursuant to paragraph (4) in respect of the construction or repowering of surface emergent tidal devices and operational hubs in the array area without having first consulted with the Isle of Anglesey County Council and shall not approve any device deployment protocol, cable management plan, decommissioning programme or updated navigational risk assessment pursuant to paragraph (4) without having first consulted Trinity House and the Maritime and Coastguard Agency, and in each case the Welsh Ministers shall have regard to the responses of those consultees.
(6) The tidal works and any parts thereof must be constructed maintained, repowered and decommissioned (as appropriate) in accordance with the documents approved pursuant to paragraph (4) above save that such documents may be revised from time to time with the agreement of the Welsh Ministers.
(7) For the purposes of paragraphs (4) and (6) above any approval to an equivalent document pursuant to a condition of a marine licence granted for the tidal works or an agreed amendment to such a document shall be deemed to be approval of the Welsh Ministers.
(8) No tidal works may commence until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) of the 2004 Act has been submitted to the Secretary of State for approval.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: