22. The undertaker may acquire compulsorily—
(a)so much of the land shown on the onshore plan within the limits of deviation as land to be acquired compulsorily and described in the book of reference as may be required for the purposes of the authorised works; and
(b)so much of the land specified in columns (1) and (2) of Schedule 2 to this Order (being land shown on the onshore plan and described in the book of reference) as may be required for the purpose specified in relation to that land in column (3) of that Schedule,
and may use any land so acquired for those purposes or for any other purposes that are ancillary to the authorised works and their operation.