PART 1PRELIMINARY

Interpretation2.

(1)

In this Order—

“the 1961 Act” means the Land Compensation Act 19614;
“the 1965 Act” means the Compulsory Purchase Act 19655;
“the 1981 Act” means the Acquisition of land Act 19816;
“the 1995 Order” means the Town and Country Planning (General Permitted Development) Order 19957;

“authorised works” means the works required to demolish the Summerway Overbridge (Network Rail asset No. 133A) and any associated temporary works authorised by the 1995 Order;

“the book of reference” means the book of reference certified by the Welsh Ministers as the book of reference for the purposes of this Order;

“building” includes any structure or erection or any part of a building, structure or erection;

“electronic transmission” means a communication transmitted—

(a)

by means of an electronic communications network; or

(b)

by other means but while in electronic form;

“the land plan” means the plan certified by the Welsh Ministers as the land plan for the purposes of this Order;

“the limits of land to be acquired or used” means the limits so shown and described on the land plan;

Network Rail” means Network Rail Infrastructure Limited (company registration number 02904587) whose registered office is 1 Eversholt Street, London NW1 2DN; and

“owner” in relation to land, has the same meaning as in section 7 (interpretation) of the 1981 Act8.

(2)

All measurements stated in any description of lands in the book of reference are approximate.

(3)

References in this Order to numbered plots are references to plot numbers shown on the land plan.