1.,Particulars of all notices under sections 54, 55 and 57 served on the highway authority relating to street works in any street which is a maintainable highway.,The undertaker concerned.,
2.,Particulars of all notices under sections 54, 55 and 57 served on street managers relating to street works in any street which is not a maintainable highway.,The undertaker concerned.,
3.,Particulars of all directions given under sections 56 and 56A.,The street authority concerned.,
4.,Particulars of all notices, consents and directions published or given by a street authority under sections 58 and 58A.,The street authority concerned.,
5.,Particulars of all notifications made by an undertaker under paragraph 2(1)(d) of Schedule 3A to the 1991 Act .,The undertaker concerned.,
6.,Particulars of all notices served by a street authority under section 66.,The street authority concerned.,
7.,Information under section 70(3) and (4A) as to completion of reinstatements.,The undertaker concerned.,
8.,Particulars of all notices given by a street authority under section 72(3).,The street authority concerned.,
9.,Particulars of all notices given by an undertaker under section 74.,The undertaker concerned.,
10.,Particulars of all notices given by a street authority under section 74.,The street authority concerned.,
11.,Description and location of street works for which plans and sections have been submitted under Schedule 4 to the 1991 Act .,The undertaker concerned.,
12.,Particulars of notices given by any relevant authority under Schedule 4 to the 1991 Act .,The relevant authority.,

1.,Every street for which the local highway authority is the street authority.,The local highway authority.,
2.,Every street which is a prospectively maintainable highway.,The local highway authority.,
3.,Every street, of which the local highway authority is aware, which is a highway but for which it is not the street authority.,The local highway authority.,
4., Every street which —     is —     a protected street ;      a street with special engineering difficulties; or      a traffic-sensitive street,     including, where appropriate, details of the parts of the street so designated and, in the case of a traffic-sensitive street, of any limited designation; or      is proposed for designation as such.    ,The street authority concerned.,
5., Description, timing and location of works for road purposes and major highway works which involve —     breaking up the highway;      opening the carriageway of a traffic-sensitive street at a traffic-sensitive time; or      the width of carriageway available for vehicular traffic being reduced —     by one or more traffic lanes;      by more than one third in a case where there are no such lanes; or      by any amount in a traffic sensitive street at a traffic-sensitive time, and any such works that are proposed.       ,The street authority concerned.,
6.,Particulars of all consents given by a street authority under section 61 together with details of any conditions.,The street authority concerned.,
7.,Details of all directions given under section 62.,The street authority concerned.,
8.,Particulars of street works licences, including details of conditions and of changes in ownership.,The street authority concerned.,
9.,Particulars of apparatus notified to the street authority under section 80(2).,The street authority concerned.,
10.,Every notice of works under section 85(2).,The authority concerned.,
11.,Details of road closures and diversions where an order under section 14 of the 1984 Act is required.,The highway authority.,
12.,The road category of each street.,The street authority concerned,


Major works,10 days,
Standard works,10 days,
Minor works,3 days,