SCHEDULES

SCHEDULE 6FOR PROTECTION OF NETWORK RAIL

Repayment of Network Rail’s costs in connection with construction

12.

The undertaker must pay to Network Rail a sum equivalent to any costs reasonably incurred by Network Rail in—

(a)

constructing any work on behalf of the undertaker as provided by paragraph 4 or in constructing any protective works as provided by paragraph 5; and

(b)

respect of the approval by the engineer of plans submitted by the undertaker and the supervision by the engineer of the construction of any relevant work.