There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Associated British Ports (Immingham Green Energy Terminal) Order 2025. Those changes will be listed when you open the content using the Table of Contents below. Any changes that have already been made by the team appear in the content and are referenced with annotations.![]()
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the affected provisions when you open the content using the Table of Contents below.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
PART 5 MISCELLANEOUS AND GENERAL
TEMPORARY RESTRICTION OR ALTERATION, ETC. OF THE USE OF STREETS OR PUBLIC RIGHTS OF WAY
LAND IN WHICH ONLY NEW RIGHTS AND RESTRICTIVE COVENANTS, ETC. MAY BE ACQUIRED
PART 1 FOR THE PROTECTION OF THE STATUTORY CONSERVANCY AND NAVIGATION AUTHORITY FOR THE HUMBER
PART 2 FOR THE PROTECTION OF THE ENVIRONMENT AGENCY
PART 5 FOR THE PROTECTION OF NETWORK RAIL
60.(1) Where under this Part of this Schedule Network Rail...
61.(1) The undertaker must not exercise the powers conferred by...
62.(1) The undertaker must before commencing construction of any specified...
64.The undertaker must— (a) at all times afford reasonable facilities...
65.Network Rail must at all times afford reasonable facilities to...
66.(1) If any permanent or temporary alterations or additions to...
67.(1) The undertaker must repay to Network Rail all reasonable...
68.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2),...
70.The undertaker must not provide any illumination or illuminated sign...
71.Any additional expenses which Network Rail may reasonably incur in...
72.(1) The undertaker must pay to Network Rail all reasonable...
75.The undertaker and Network Rail may, subject in the case...
76.Nothing in this Order, or in any enactment incorporated with...
77.The undertaker must give written notice to Network Rail where...
PART 6 FOR THE PROTECTION OF NORTH EAST LINCOLNSHIRE COUNCIL (AS LEAD LOCAL FLOOD AUTHORITY)
81.(1) Before beginning to construct any specified work, the undertaker...
82.(1) Without limitation on the scope of paragraph 81, the...
83.(1) Subject to sub-paragraph (3), any specified work, and all...
84.(1) Subject to sub-paragraph (2) the undertaker must from the...
85.Subject to paragraph 84, if by reason of the construction...
86.(1) The undertaker must repay the authority all proper and...
87.(1) Without affecting the other provisions of this Part of...
89.Any dispute arising between the undertaker and the authority under...
PART 7 FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER
PART 8 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 9 FOR THE PROTECTION OF THE NORTH EAST LINDSEY DRAINAGE BOARD
116.Without limiting paragraph 115, the requirements which the Board may...
117.(1) Subject to sub-paragraph (2), any specified work, and all...
118.If by reason of the construction of any specified work...
119.The undertaker must pay to the Board all costs, charges...
120.(1) Without limiting the other provisions of this Part of...
122.Any dispute between the undertaker and the Board under this...
PART 10 FOR THE PROTECTION OF CLDN PORTS KILLINGHOLME LIMITED
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including:
The data on this page is available in the alternative data formats listed: