Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
9.—(1) Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3) (cases in which land is to be treated as not being operational land) of the 1990 Act.
(2) The authorised development may be carried out or continue to be carried out, and the airport may be operated or continue to be operated, pursuant to this Order notwithstanding the initiation of development pursuant to any planning permission which may be physically incompatible with the authorised development or inconsistent with any provision of this Order.
(3) Any planning permission which has been initiated prior to the commencement of the authorised development pursuant to this Order may continue to be lawfully implemented thereafter notwithstanding any physical incompatibility with the authorised development or inconsistency with any provision of this Order.
(4) Any conditions of any planning permission granted prior to the date of this Order that are incompatible with the requirements of this Order or the authorised development shall cease to have effect from the date the authorised development is commenced and for the purpose of this article planning permissions deemed to be granted pursuant to the 2015 Regulations shall be deemed to be granted prior to the date of this Order.
(5) Where the undertaker identifies an incompatibility between a condition of a planning permission and this Order that engages paragraph (4), it must notify the relevant planning authority and use reasonable endeavours to notify the current beneficiary of the affected planning permission as soon as reasonably practicable.
(6) Subject to paragraph (7), nothing in this Order restricts any person from seeking or implementing, or the relevant planning authority from granting, planning permission for development within the Order limits.
(7) The undertaker must not exercise the permitted development right in Class F of Part 8 (transport related development) of Schedule 2 (permitted development rights) to the 2015 Regulations for any development on the areas labelled Work No. 38 (habitat enhancement area and flood compensation area at Museum Field), Work No. 41 (ecological area at Pentagon Field) or Work No. 43 (water treatment works) on the works plans.
(8) In this article—
(a)“initiate” means when development of land is taken to be begun in accordance with section 56(1) (time when development begun) of the 1990 Act, and “initiated” and “initiation” are defined accordingly; and
(b)“planning permission” means planning permission granted under the 1990 Act including planning permission deemed to be granted under article 3 (permitted development) and Classes F, G, I, J, K, L, M and N of Part 8 of Schedule 2 to the 2015 Regulations.
Commencement Information
I1Art. 9 in force at 12.10.2025, see art. 1
Section 56 was amended by paragraph 10 of Schedule 6 and paragraph 10(2) of Schedule 7 to the Planning and Compensation Act 1991 (c. 34), paragraph 2 of Schedule 12 to the Localism Act 2011 (c. 20), paragraph 3 of Schedule 4 to the Infrastructure Act 3025 (c. 7), paragraph 3(2) of Schedule 14 to the Environment Act 2021 (c. 30) and sections 113(3) and 114(2) of, and paragraph 10(1) of Schedule 7 to, the Levelling-up and Regeneration Act 2023 (c. 55).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: