84.—(1) This paragraph applies insofar as—
(a)the construction of the authorised development would have the potential to have an effect on the exercise by CF Fertilisers of its rights in connection with the proposed CF pipeline within the Order limits;
(b)the construction of the respective authorised developments may be undertaken within the Order limits concurrently; or
(c)the construction of one of the respective authorised developments would have an effect on the operation or maintenance of the other respective authorised development or access to it.
(2) Where this paragraph applies the undertaker and CF Fertilisers must—
(a)co-operate with each other with a view to ensuring—
(i)the compatibility of the respective authorised developments;
(ii)the co-ordination of construction programming and the carrying out of the respective authorised developments;
(iii)that access for the purposes of constructing the respective authorised developments is maintained for the undertaker, CF Fertilisers and their respective employees, contractors and sub-contractors;
(iv)the undertaker and CF Fertilisers have the appropriate risk assessments, method statements (RAMS) and construction design management (CDM) in place and are able to comply with their obligations in this respect; and
(v)that operation, maintenance and access to the respective authorised developments is maintained for the undertaker and CF Fertilisers;
(b)use reasonable endeavours to avoid any conflict arising from the carrying out of the respective authorised developments.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: