xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULES

SCHEDULE 9E+W+SPROTECTIVE PROVISIONS

PART 10E+W+SFOR THE PROTECTION OF THE KUMATAGE FIELD

Line of orientationE+W+S

6.  The licensee shall not carry out, nor procure the carrying out of, the licensee’s works in any way that would prevent the undertaker from constructing and maintaining the wind turbine generators comprised in the authorised development in a layout consistent with the primary lines of orientation.

Commencement Information

I1Sch. 9 Pt. 10 para. 6 in force at 3.8.2023, see art. 1