2023 No. 442

Infrastructure Planning

The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) (Correction) Order 2023

Made

Coming into force

The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 20221 (“the Order”), which granted development consent within the meaning of the Planning Act 20082 (“the Act”) contains correctable errors within the meaning of paragraph 1 of Schedule 4 to the Act.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, and before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicant3 for the corrections of errors and omissions in the Order.

In accordance with paragraph 1(7) of Schedule 4 to the Act, the Secretary of State has informed the relevant local planning authority for the area in which the land to which the Order relates is situated that the request has been received.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraph 1(4) and 1(8) of Schedule 4 to the Act, makes the following Order—

Citation and commencement1

This Order may be cited as the Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) (Correction) Order 2023 and comes into force on 20th April 2023.

Corrections2

The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 is corrected as set out in the table in the Schedule to this Order, where—

a

column 1 sets out where the correction is to be made;

b

column 2 sets out how the correction is to be made; and

c

column 3 sets out the text to be substituted, inserted or omitted.

Signed by authority of the Secretary of State for Energy, Security and Net Zero

David WagstaffDeputy Director Energy Infrastructure PlanningDepartment for Energy, Security and Net Zero

SCHEDULECorrectable Errors

Article 2

Provision

How correction is to be made

Text to be substituted, inserted or omitted

Article 2 (interpretation) “carbon capture and compression plant”

After “No 7” add

“as set out”

Article 2 (interpretation) “carbon capture and compression plant”

After “Schedule 1” add

“and as”

Article 21(3)

Substitute “4A and 4B” for

“4A or 4B”

Article 21(3)

After “(1) are” add

“respectively”

Schedule 9 (procedure for discharge of requirements) paragraph 4(2)(2) sub paragraph (ii)

Substitute “pursuan” for

“pursuant”

EXPLANATORY NOTE

(This note is not part of the Order)

This Order corrects errors in the Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, which granted development consent under the Planning Act 2008, following a request made under paragraph 1(5)(a) of Schedule 4 to that Act.