xmlns:atom="http://www.w3.org/2005/Atom" xmlns:atom="http://www.w3.org/2005/Atom"
26. The undertaker must repay to the Agency all reasonable costs, charges and expenses which the Agency may reasonably incur—E+W
(a)in the examination or approval of plans under this Part of this Schedule;
(b)in the inspection of the construction of the specified works or any protective works required by the Agency under this Part of this Schedule; or
(c)in the carrying out of any surveys or tests by the Agency which are reasonably required in connection with the construction of the specified works.
Commencement Information
I1Sch. 9 para. 26 in force at 6.6.2022, see art. 1