The Little Crow Solar Park Order 2022

Operation of generating station

11.—(1) The undertaker is authorised to operate and use the generating station for which development consent is granted by this Order.

(2) Paragraph (1) does not relieve the undertaker of any requirement to obtain any permit or licence under any other legislation that may be required from time to time to authorise the operation of an electricity generating station.