SCHEDULE 12PROTECTIVE PROVISIONS

PART 5FOR THE PROTECTION OF CADENT GAS LIMITED

Interpretation

54.—(1) Where in consequence of the proposed construction of any part of the authorised works, Network Rail or Cadent requires the removal of apparatus under paragraph 48(2) or Cadent makes requirements for the protection or alteration of apparatus under paragraph 50, Network Rail must use its reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised works and taking into account the need to ensure the safe and efficient operation of Cadent’s undertaking and Cadent must use its best endeavours to co-operate with Network Rail for that purpose.

(2) Whenever Cadent’s consent, agreement or approval is required in relation to plans, documents or other information submitted by Cadent or the taking of action by Cadent, it must not be unreasonably withheld or delayed.