Grant of a spaceport licence: prescribed criteria for horizontal spaceports

35.—(1) Where the proposed spaceport is a horizontal spaceport, the proposed spaceport must be located at an aerodrome which is—

(a)either—

(i)certified, or

(ii)CAA licensed, and

(b)NASP directed.

(2) For the purposes of this regulation “NASP directed” in relation to an aerodrome means an aerodrome which is subject to the direction of the Secretary of State under sections 12, 13, 13A, 14 and 15 of the Aviation Security Act 1982(1).

Grant of a spaceport licence: safety case requirement

36.—(1) An applicant must carry out a safety case which, unless the circumstances in paragraph (2) apply, meets the requirements in paragraphs (3) to (7).

(2) The circumstances referred to in paragraph (1) are that the applicant’s application is not based on an actual vehicle.

(3) The applicant’s safety case must take into account—

(a)the interests of any operator applicant,

(b)the interests of any other known user of the proposed spaceport site, and

(c)if the proposed spaceport is a horizontal spaceport—

(i)the interests of the aerodrome licence holder, and

(ii)the interests of any other aerodrome user.

(4) The applicant’s safety case must as a minimum contain the following information—

(a)a description of the proposed spaceport, including a description of—

(i)the licensed activities proposed to be conducted at that spaceport,

(ii)the spaceflight activities proposed to be conducted at that spaceport, and

(iii)the activities of any other known spaceport user;

(b)if the proposed spaceport is a horizontal spaceport, a description of the aerodrome;

(c)a description of the vicinity of the proposed spaceport, including identification of any areas, developments or features which could affect the assessment of risks or hazards or the mitigation measures to be applied in the event of an emergency occurring at the spaceport;

(d)a plan of the proposed spaceport identifying and showing the proposed location of—

(i)any known spaceport infrastructure including runways, taxiways, launch pads, test stands and launch vehicle parking areas,

(ii)any proposed physical barrier under regulation 172(2),

(iii)any proposed installations including maintenance facilities, integration facilities, hangars or any other buildings,

(iv)any proposed hazardous material storage facilities to be designated under regulation 158, including, if known, the types and maximum quantities to be stored at each hazardous material storage facility,

(v)any proposed area or buildings for handling or venting of any hazardous material, and

(vi)any proposed static engine or other test areas;

(e)a description of any spaceflight activities which the applicant believes likely to be carried out from the spaceport, including a description of any carrier aircraft or launch vehicle to be launched and any payload to be carried by such an aircraft or vehicle if the spaceport licence is granted, including—

(i)any associated infrastructure requirements;

(ii)any associated operational requirements, such as integration facilities and hangars;

(iii)any operating characteristics which may affect licensed activities;

(iv)any rescue and firefighting requirements;

(v)any hazardous material to be used by a carrier aircraft, launch vehicle or payload, or to be stored at the spaceport.

(5) The applicant’s safety case must include, in relation to the operations and activities listed in paragraph (6)—

(a)identification of each major accident hazard that could arise during the operation or activity,

(b)an assessment of the likelihood of it arising and of the severity of the consequences if it does occur, and

(c)a description of the prevention and mitigation measures that will be applied to ensure that the risks identified are as low as reasonably practicable.

(6) The operations and activities to which paragraph (5) refers are—

(a)the transporting, handling and storing of any hazardous material at the spaceport,

(b)the integration of a payload with a launch vehicle at the spaceport,

(c)the integration of a carrier aircraft with a launch vehicle at the spaceport,

(d)any testing of a type described in regulation 161 (requirement to designate appropriate area for static engine etc. testing) at the spaceport, and

(e)any other proposed licensed activities or spaceflight activities which may give rise to a major accident hazard.

(7) Taking into account the findings of the assessment required under paragraph (5), the applicant’s safety case must, except where regulation 37(2) applies—

(a)identify that a safety clear zone is required,

(b)define the area that will comprise the safety clear zone,

(c)stipulate the times that the safety clear zone will be in place,

(d)set out the measures the applicant will take to ensure that a safety clear zone is put in place and is monitored, and

(e)set out the arrangements the applicant will have in place to ensure that no person, other than a person permitted to be present under regulation 157(3)(d), is inside a safety clear zone.

(8) Where the circumstances in paragraph (2) apply, the applicant’s safety case must—

(a)be based on the representative vehicle,

(b)take into account the matters listed in paragraph (3), as far as these are known to the applicant,

(c)contain as much of the information set out in paragraph (4) as is known to the applicant,

(d)include an assessment that meets, as far as possible, the requirements of paragraph (5), and

(e)take into account the assessment carried out under sub-paragraph (d), and unless regulation 37(2) applies, as far as possible satisfy the requirements in paragraph (7).

(9) In this regulation “aerodrome licence holder” means the holder of the CAA licence or aerodrome certificate for the aerodrome at which the proposed horizontal spaceport is to be located in accordance with regulation 35(1).

Grant of a spaceport licence: safety clear zone requirement

37.—(1) An applicant must, unless paragraph (2) applies, show that it will be able to put in place an appropriate safety clear zone to ensure that the risk to any person from blast overpressure, fragmentation debris, thermal radiation or toxic release will be as low as reasonably practicable during any hazardous pre-flight and post-flight operations.

(2) Paragraph (1) does not apply if the safety case demonstrates that a safety clear zone will not be required for the hazardous pre-flight or post-flight operations.

(3) For the purposes of paragraph (1), an appropriate safety clear zone is one that is determined by the assessment made in the applicant’s safety case under regulation 36(7).

Grant of a spaceport licence: siting assessment requirement

38.—(1) An applicant must conduct a siting assessment that meets the requirements in this regulation.

(2) The applicant’s siting assessment must—

(a)relate to the site of the proposed spaceport,

(b)subject to paragraph (4), be based on the actual launch vehicle or vehicles, and

(c)result in a numerical estimate of the annualised risk of death or serious injury to members of the public posed by the spaceflight activities proposed.

(3) The level of risk determined under paragraph (2)(c) must be acceptable to the regulator.

(4) Where the applicant’s application is not based on an actual vehicle, the applicant’s siting assessment must be based on the representative vehicle.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules as a PDF

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources