PART 2
Amendment of Schedule 3 (publicity for applications for planning permission)18.
“(f)
date giving a period (as the case may be, and subject to (fa)) of—
(i)
21 days beginning with the date when the notice is first displayed or accessible on or near the site or served on an owner and/or occupier of adjoining land under article 15(4) or (5);
(ii)
14 days beginning with the date when the notice is published in a newspaper; or
(iii)
21 days beginning with the date when the notice is served on an infrastructure manager under article 16;
and when computing the number of days in sub-paragraphs (i) and (ii), any day which is a public holiday must be disregarded;
(fa)
in the case of an application for public service infrastructure development, date giving a period of—
(i)
18 days beginning with the date when the notice is first displayed or accessible on or near the site or served on an owner and/or occupier of adjoining land under article 15(4) or (5);
(ii)
14 days beginning with the date when the notice is published in a newspaper; or
(iii)
18 days beginning with the date when the notice is served on an infrastructure manager under article 16,
and when computing the number of days in sub-paragraphs (i) and (ii), any day which is a public holiday must be disregarded.”.