The Immingham Open Cycle Gas Turbine Order 2020

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about advanced features

Advanced Features

 Help about opening options

Opening OptionsExpand opening options

Changes over time for:

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for The Immingham Open Cycle Gas Turbine Order 2020. Help about Changes to Legislation

E+W

Work No. 1 – OCGT power station, being an open cycle gas turbine generating station with a gross capacity of up to 299 megawatts, comprising—

(a)gas turbine and turbine hall buildings;

(b)electrical generator;

(c)stack;

(d)auxiliary cooling equipment or system;

(e)gas turbine air intake filters;

(f)banks of finfan coolers;

(g)nitrogen oxide emissions control equipment;

(h)transformers;

(i)a switchyard, associated switch gear and ancillary equipment;

(j)a gas receiving area, gas control facilities and gas reception building;

(k)lubricating oil, hydraulic oil and chemical storage tanks and equipment;

(l)continuous emissions monitoring system;

(m)raw water and fire water storage tanks;

(n)water treatment facilities, demineralised water treatment works, including storage tanks;

(o)oily water and waste water treatment plant building and basin;

(p)fire fighting equipment, buildings and distribution pipework;

(q)permanent plant laydown area;

(r)auxiliary plant, buildings, enclosures and structures;

(s)mechanical, electrical, gas, telecommunications and water networks, pipework, cables, racks, infrastructure, instrumentation and utilities, including connections between parts of this Work No. 1 and Work Nos 4, 5 and 6;

(t)workshop buildings and stores;

(u)electrical, control, administration and welfare buildings; F1...

(v)storm water attenuation system; [F2and

(w)synchronous condenser.]

Textual Amendments

Commencement Information

I1Sch. 1 in force at 1.9.2020, see art. 1

Back to top

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?