PART 3 ACQUISITION AND POSSESSION OF LAND
PART 4 MISCELLANEOUS AND GENERAL
SCHEDULES
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
PART 1 FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS
PART 2 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 3 FOR THE PROTECTION OF DRAINAGE AUTHORITIES AND THE ENVIRONMENT AGENCY
16.(1) The following provisions of this Part of this Schedule...
17.(1) Before beginning to construct any specified work, Network Rail...
18.Without limitation on the scope of paragraph 17, the requirements...
19.(1) Subject to sub-paragraph (2), any specified work, and all...
20.(1) Subject to sub-paragraph (5) Network Rail must from the...
21.Subject to paragraph 23, if by reason of the construction...
23.Nothing in paragraphs 19(4), 20(3), 21, 22(3) and (4) authorises...
24.Network Rail must indemnify the drainage authority in respect of...
25.(1) Without affecting the other provisions of this Part of...