Search Legislation

The Nuclear Safeguards (EU Exit) Regulations 2019

Status:

This is the original version (as it was originally made).

Additional reporting obligations arising from relevant international agreements and from obligations resulting from international trade

This section has no associated Explanatory Memorandum

19.—(1) When an operator provides the ONR with the information which is listed in paragraph (2), the operator must identify, separately for each obligation in each of the reports and notifications listed in the relevant international agreement, unless otherwise stipulated by that agreement, any qualifying nuclear material which is subject to a relevant safeguards obligation and must use the appropriate obligation code if one has been published by the ONR.

(2) The following information is listed in this paragraph—

(a)an initial book inventory, provided for in regulation 13;

(b)an inventory change report, including an ending book inventory, provided for in regulation 14;

(c)a material balance report and a physical inventory listing provided for in regulation 15;

(d)advance notification of intended imports and exports provided for in regulations 21 and 22.

(3) Where an operator—

(a)holds qualifying nuclear material, which has been transferred into the United Kingdom, under obligations or requirements concerning international trade, which ensure that qualifying nuclear material is only available for peaceful purposes, and are respectively described in paragraph (4) (“obligations concerning international trade”) and in paragraph (5) (“requirements concerning international trade”); and

(b)provides the ONR with the information which is listed in paragraph (2),

the operator must identify, separately for each obligation and requirement concerning international trade in each of the reports and notifications, unless otherwise stipulated by the relevant obligation or requirement, any qualifying nuclear material which is subject to an obligation or requirement concerning international trade and must use the appropriate obligation code if one has been published by the ONR.

(4) The obligations concerning international trade arise where an operator holds qualifying nuclear material which has been transferred into the United Kingdom before commencement day, either directly or through a third country, in accordance with any of the following—

(i)the Agreement for co-operation in the peaceful uses of nuclear energy between the European Atomic Energy Community and the Government of the Republic of Kazakhstan, signed in Brussels on 5th December 2006;

(ii)the Agreement for co-operation in the peaceful uses of nuclear energy between the European Atomic Energy Community and the Government of the Republic of Uzbekistan, signed in Brussels on 6th October 2003;

(iii)the Agreement between the European Atomic Energy Community and the Cabinet of Ministers of Ukraine for Co-operation in the Peaceful Uses of Nuclear Energy, signed in Kiev on 28th April 2005;

(iv)the Agreement for co-operation in the peaceful uses of nuclear energy between the European Atomic Energy Community (Euratom) and the Government of the Argentine Republic, signed at Brussels, on 11th June 1996;

(v)the Agreement between the European Atomic Energy Community (Euratom) and the Government of the United States of Brazil for cooperation concerning the peaceful uses of atomic energy, signed at Brasilia, on 9th June 1961; and

(vi)a contract, to which the operator is a party, concluded, before commencement day, on the basis of Articles 52(2), 64, 75(c) or another relevant provision in Chapter 6 of the Treaty establishing the European Atomic Energy Community.

(5) The requirements concerning international trade arise where an operator holds qualifying nuclear material which has been transferred into the United Kingdom before, on or after commencement day, under the terms of a requirement, which is set out in a licence issued by the ONR under the Import of Goods (Control) Order 1954(1) or an order made by the Secretary of State under section 1 of the Import, Export and Customs Powers (Defence) Act 1939(2).

(6) In respect of each relevant international agreement and each obligation and requirement concerning international trade, the ONR must publish on its website, and make available in writing on request, any obligation codes which must be used by an operator in respect of that relevant international agreement or obligation or requirement concerning international trade.

(7) Unless specifically prohibited in the relevant international agreement or obligation or requirement concerning international trade, the separate reporting requirements set out in paragraphs (1) and (3) do not preclude the physical mixing of qualifying nuclear materials.

(8) Paragraphs (1) to (7) do not apply to the Agreement with the Agency nor to the Additional Protocol, dated 7th June 2018, entered into between the United Kingdom and the Agency and which is additional to the Agreement with the Agency.

(1)

S.I. 1954/23 as amended by S.I 2014/251.

(2)

1939 c.69 2 and 3 Geo 6 s amended by Customs and Excise Management Act 1979 (c.2) and the Export Control Act 2002 (c.28) sections 15(2)(a), 16(2) and 16(7).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources