SCHEDULE 1130PROTECTIVE PROVISIONS

PART 1FOR THE PROTECTION OF ELECTRICITY, GAS, WATER AND SEWERAGE UNDERTAKERS

I11

For the protection of the utility undertakers referred to in this part of this Schedule (save for National Grid which is protected by Part 3 of this Schedule, Western Power Distribution (South Wales) plc which is protected by Part 4 of this Schedule, Dŵr Cymru Cyfyngedig which is protected by Part 5 of this Schedule, Abergelli Solar Limited which is protected by Part 6 of this Schedule, and Wales and West Utilities Limited which is protected by Part 7 of this Schedule), the following provisions have effect, unless otherwise agreed in writing between the undertaker and the utility undertakers concerned.