Exemptions from section 4(1)(b) of the Act (prohibition on unlicensed transmission of electricity for supply)
This section has no associated Explanatory Memorandum
2.—(1) Each person described in the first column of the table is granted exemption from section 4(1)(b) of the Act() (prohibition on unlicensed transmission of electricity for supply) in respect of transmission taking place over the relevant transmission system connected to the generating station described in the corresponding entry in the second column for the period described in paragraph (2).
(2) The period in this paragraph, in respect of each person named in the first column of the table—
(a)begins with the date specified in the corresponding entry in the third column; and
(b)ends with the date specified in the corresponding entry in the fourth column.
(3) But if the transmission system connected to the generating station described in the second column of the table is transferred to a successful bidder before the date specified in the fourth column of the table, the exemption ceases to apply on the day after the day on which the transfer is completed.
(4) In this article—
(a)“successful bidder” means a person to whom, as a result of a tender exercise, an offshore transmission licence within the meaning of section 6C(5)() of the Act (competitive tenders for offshore transmission licences) has been or is to be granted in respect of the relevant transmission system;
(b)“relevant transmission system” means, in relation to a person described in the first column of the table, the transmission system connected to the generating station described in the corresponding entry in the second column of the table.
(1) | (2) | (3) | (4) |
---|
Name of person | Description of generating station | Exemption start date | Exemption end date |
---|
Race Bank Wind Farm Limited, a company registered in England and Wales with company number 05017828. | Race Bank Offshore Wind Farm located approximately 27 kilometres to 33.3 kilometres from the shore, off the North Norfolk coast, its coordinates at its central point being Latitude 53.276479 and Longitude 0.841785. | 12th March 2019 | 9th November 2019 |
Galloper Wind Farm Limited, a company registered in England and Wales with company number 07320597. | Galloper Offshore Wind Farm located approximately 27 kilometres to 37.3 kilometres from the shore, off the Suffolk coast, its coordinates at its central point being Latitude 51.893 and Longitude 2.034. | 13th September 2019 | 12th March 2020 |
Walney Extension Limited, a company registered in England and Wales with company number 07306956. | Walney Extension Wind Farm located approximately 19 kilometres to 29 kilometres from the shore, in the Irish Sea, off Walney Island coast in Cumbria, its coordinates at its central point being Latitude 54.087619 and Longitude -3.737710. | 21st September 2019 | 12th June 2020 |
Rampion Offshore Wind Limited, a company registered in England and Wales with company number 07199847. | Rampion Offshore Wind Farm located approximately 13 kilometres to 17.2 kilometres from the shore, in the English Channel, off the Sussex coast, its coordinates at its central point being Latitude 50.668 and Longitude -0.276. | 21st May 2019 | 27th November 2020 |