Article 2
Work No. 1 — A railway, 2031 metres in length, being a realignment of the Stamford lines, commencing by a junction with the East Coast Main Line at a point 227 metres north-east of the junction of Enterprise Way with Bretton Way and terminating by a junction with the East Coast Main Line at a point 123 metres north-east of the bridge carrying Hurn Road above the Werrington Drain.
Work No. 1 includes an underpass under the realigned Stamford lines.
Work No. 2 — A railway, 2982 metres in length, commencing by a junction with Work No. 1 at a point 270 metres south-west of the junction of Mead Close with The Mead passing under the East Coast Main Line and terminating by a junction with the Great Northern Great Eastern railway line at a point 200 metres north-west of the junction of Redbridge with Hodgson Avenue.
Work No. 3 — A footbridge, over the East Coast Main Line and Works Nos. 1 and 2, commencing at a point 228 metres north of the junction of Coningsby Road with Stirling Way and terminating at a point 82 metres north-east of its commencement.
Work No. 3A — A temporary footbridge, over the East Coast Main Line, commencing at a point 223 metres south-west of the junction of the entrance to Rattan House with Papyrus Way and terminating at a point 41 metres south-west of its commencement.
Work No. 4 — A watercourse, being a diversion of Brook Drain, commencing at a point 220 metres north-east of the junction of Coningsby Road with Stirling Way and terminating at a point 270 metres south-west of the junction of the entrance to Rattan House with Papyrus Way.
Work No. 5 — A road, forming a junction with Hurn Road, commencing at a point 87 metres south-west of the bridge carrying the A15 over the Great Northern Great Eastern railway line and terminating at a point 359 metres south of the junctions of Gasworks Road, Waterworks Lane and Lincoln Road.
Work No. 6 — A bridge, to carry utility apparatus together with a footpath, bridleway and cycle track over the Great Northern Great Eastern Line and Work No. 2, commencing at a point 25 metres east of the bridge carrying the A15 over the Great Northern Great Eastern railway line and terminating at a point 76 metres north-west of its commencement.
Work No. 6 includes the demolition of the existing water pipe bridge.
Work No. 7A — A temporary bridge, over Marholm Brook, commencing at a point 95 metres north-west of the junction of Coningsby Road with Stirling Way and terminating at a point 10 metres north of its commencement.
Work No. 7B — A temporary bridge, over Marholm Brook, commencing at a point 132 metres north-west of the junction of Coningsby Road with Stirling Way and terminating at a point 10 metres north-east of its commencement.
Work No. 8 — A bridge, being an extension to the existing Lincoln Road Bridge, to carry that road over Work No. 2, commencing at a point 27 metres north-west of the bridge carrying Old Lincoln Road over the Great Northern Great Eastern railway line and terminating at a point 9 metres north-east of its commencement.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: