The East Anglia THREE Offshore Wind Farm Order 2017

Details of licensed marine activities

3.  Such activities are authorised in relation to the construction, maintenance and operation of—

(1) Work No. 2 (phase 2) – up to three offshore electrical stations fixed to the seabed within the area shown on the works plan by one of two foundation types (namely jacket or gravity base).

(2) Work No. 3 (phase 2) – a network of subsea cables within the area shown on the works plan between the offshore electrical stations comprising Work No. 2 and for the transmission of electricity and electronic communications including one or more cable crossings.

(3) Work No. 5A (phase 2) – up to two export cables between Work No. 2 and Work No. 5B consisting of subsea cables along routes within the Order limits seaward of MHWS including one or more cable crossings.

(4) In connection with such Works No. 2, 3 and 5A and to the extent that they do not otherwise form part of any such work, further associated development comprising such other works as may be necessary or expedient for the purposes of or in connection with the relevant part of the authorised scheme and which fall within the scope of the work assessed by the environmental statement and the provisions of this licence.

(5) In connection with such Works No. 2, 3 and 5A, ancillary works within the Order limits which have been subject to an environmental impact assessment recorded in the environmental statement comprising—

(a)temporary landing places, moorings or other means of accommodating vessels in the construction and/ or maintenance of the authorised scheme; and

(b)marking buoys, beacons, fenders and other navigational warning or ship impact protection works.