Search Legislation

The National Grid (Richborough Connection Project) Development Consent Order 2017

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

UK POWER NETWORKS WORKS

In the City of Canterbury

Work No.4A — PX route temporary diversion

Works to allow the construction and installation of two single circuit 132kV overhead electric lines supported by wooden poles and the installation of conductors, insulators and fittings between pylons PX8 and PX9, as shown on Works Plan Sheet 2.

Work No.4B – PX route temporary diversion

Works to allow the construction and installation of two single circuit 132kV overhead electric lines supported by wooden poles and the installation of conductors, insulators and fittings between pylons PX44 and PX46. The removal of existing pylon PX45 and associated conductors, insulators and fittings as shown on Works Plan Sheet 10.

In the District of Thanet

Work No.4C — PX route temporary diversion

Works to allow the construction and installation of two single circuit 132kV overhead electric lines supported by wooden poles and the installation of conductors, insulators and fittings between pylons PX56 and PX60. The removal of existing pylons PX57, PX58 and PX59 and associated conductors, insulators and fittings as shown on Works Plan Sheets 12 and 13.

Work No.5A — Temporary diversion of part of the PY route.

Works to allow the temporary diversion of part of the 132kV overhead electric line as shown on Works Plan Sheets 12 and 13 comprising the construction and installation of a single circuit 132kV overhead electric line supported by wooden poles and the installation of conductors, insulators and fittings between pylons PY19 and PY20TB1.

Work No.5B — Temporary diversion of part of the PY route.

Works to allow the temporary diversion of part of the 132kV overhead electric line as shown on Works Plan Sheets 12 and 13 comprising the construction and installation of a single circuit 132kV overhead electric line supported by wooden poles and the installation of conductors, insulators and fittings between pylons PY19 and PY20TA1.

Work No.5C —PY route

Works to construct and install a new section of 132kV overhead electricity line between PY19 and PY22 as shown on Works Plan Sheet 12 and 13. The overhead line consists of 6 pylons and the installation of conductors, insulators and fittings.

Work No.5D – Removal of part of the PY route

Works to allow the removal of part of the 132kV PY route between PY19 and PY22 as shown on Works Plan Sheets 12 and 13 comprising the removal of existing pylons PY20 and PY21 and the two single circuit 132kV overhead electric line temporary wooden pole diversion between pylons PY19 and PY20TB1 and between pylons PY19 and PY20TA1 and all associated conductors, insulators and fittings.

In the City of Canterbury

Work No.6A — PX route removal

Works to allow the removal of 1.3km of the 132kV PX route overhead electric line commencing at the Canterbury South 132kV Substation PX connection and terminating at Cable Sealing End pylon PX6, including the removal of 6 pylons (PX2 to PX 5, PX5A and PX 6), and associated conductors, insulators and fittings, as shown on Works Plan Sheet 1.

Work No.6B — PX route removal

Works to allow the removal of 9.7km of the 132kV PX route overhead electric line commencing at Cable Sealing End pylon PX7 as shown on Works Plan Sheet 2, and terminating at pylon PX44 as shown on Works Plan Sheet 10 to include the removal of the two single circuit 132kV overhead electric lines between pylons PX8 and PX9 as shown on Works Plan Sheet 2 including the removal of 37 pylons, the wooden poles and associated conductors, insulators and fittings.

Work No.6C — PX route removal

Works to allow the removal of the two single circuit 132kV overhead electric lines commencing at pylon PX44 and terminating at pylon PX46 as shown on Works Plan Sheet 10, including the removal of the wooden poles and associated conductors, insulators and fittings.

In the City of Canterbury and the District of Thanet

Work No.6D — PX route removal

Works to allow the removal of 2.6km of the 132kV PX route overhead electric line commencing at pylon PX46 as shown on Works Plan Sheet 10 and terminating at pylon PX56 as shown on Works Plan Sheet 12 including the removal of 11 pylons and associated conductors, insulators and fittings.

In the District of Thanet

Work No.6E — PX route removal

Works to allow the removal of the two temporary single circuit 132kV overhead electric lines commencing at pylon PX56 as shown on Works Plan Sheet 12 and terminating at pylon PX60 as shown on Works Plan Sheet 13, including the removal of the wooden poles and associated conductors, insulators and fittings.

In the District of Thanet and the District of Dover

Work No.6F — PX route removal

Works to allow the removal of 5.2km of the 132kV PX route overhead electric line commencing at pylon PX60 as shown on Works Plan Sheet 13 and terminating at the Richborough 132kV Substation PX connection as shown on Works Plan Sheet 17 including the removal of 19 pylons and associated conductors, insulators and fittings.

Back to top

Options/Help