Article 11

SCHEDULE 5STREETS SUBJECT TO ALTERATION OF LAYOUT

(1) Area(2) Street to be altered(3) Description of alteration(4) Works number
In the London Borough of Enfield.The section of Advent Way shown within plot 31 on the land plans.Works to widen the existing access from Advent Way into the Edmonton EcoPark, including modification to kerb lines and pavements within plot 31.4(g)
In the London Borough of Enfield.The section of Lee Park Way shown within plots 14, 15, 21, 22 and 32 on the land plans.

Works to reposition footpaths and cycle paths that run along the section of Lee Park Way falling within plots 14, 15, 21, 22 and 32.

Works to create a new access branching off the section of Lee Park within plot 15, into the Edmonton EcoPark. The installation of vehicle barriers on Lee Park Way near the new access from Lee Park Way into the Edmonton EcoPark and on Lee Park Way near its junction with Advent Way.

4(i) and (j)
In the London Borough of Enfield.Deephams Farm Road.Works to upgrade Deephams Farm Road to make it suitable for operational and construction traffic, including provision of a new security barrier and gatehouse, works to improve the road surface, and new fencing.4(k), (m) and (n)
In the London Borough of Enfield.

Land on the verge of Lee Park Way within plots 28 and 29 as shown on the land plans.

Modification to kerb lines and pavements within these verges that fall within plots 28 and 29.4(q)
In the London Borough of Enfield.Footpath within plot 21 as shown on the land plans.Creation of a new footpath to branch out from the existing footpath within this plot 21 south east towards Advent Way.4(r)