xmlns:atom="http://www.w3.org/2005/Atom"

SCHEDULE 2REQUIREMENTS

Notices

8.  The undertaker must give notice of the following events to the relevant planning authority where practicable prior to the date on which the event is intended to first occur and in any event within 7 days of the first occurrence of the event—

(a)the commencement of the authorised development;

(b)the issue of the certificate of practical completion for the electricity and heat generating station; and

(c)the commencement of the full operation of the electricity and heat generating station (following the completion of any period of testing and commissioning).