The North London Heat and Power Generating Station Order 2017

Operation of authorised development

6.—(1) The undertaker is authorised to operate the authorised development.

(2) Other than as set out in this Order, this article does not relieve the undertaker of any requirement to obtain any permit or licence or any other obligation under any other legislation that may be required to authorise the operation of any part of the authorised development.