5.—(1) Subject to the provisions of this Order including the requirements in Schedule 2 (requirements), the undertaker is granted development consent for the authorised development to be carried out within the Order limits.
(2) Any enactment applying to land within or adjacent to the Order limits has effect subject to the provisions of this Order.
(3) Despite anything in this Order or shown on the works plans, the undertaker may construct either Work No. 2A or Work No. 2B but not both.