The Brechfa Forest Wind Farm Connection Order 2016
en
King's Printer of Acts of Parliament
2016-10-19
INFRASTRUCTURE PLANNING
This Order authorises Western Power Distribution (South Wales) Plc (referred to in this Order as the undertaker) to construct and maintain a 132kV above ground electric line approximately 28.6km long in Carmarthenshire, Wales. The electric line runs from a new substation serving the Brechfa Forest West Wind Farm to the existing Swansea 132kV above ground electric line and includes a section of approximately 3.56km of undergrounding. The Order permits the undertaker to acquire, compulsorily or by agreement, rights in land and to use land for this purpose. A copy of the plans and book of reference referred to in this Order and certified in accordance with article 33 (certification of plans) of this Order may be inspected free of charge at Carmarthenshire County Borough Council of County Hall, Carmarthen SA31 1JP.