20.Statutory authority to override easements and other rights
21.Time limit for exercise of authority to acquire rights compulsorily
24.Application of the Compulsory Purchase (Vesting Declarations) Act 1981
27.Temporary use of land for carrying out the authorised development
28.Temporary use of land for maintaining and decommissioning the authorised development
STREETS SUBJECT TO PERMANENT AND TEMPORARY ALTERATION OF LAYOUT
PART 1 THOSE PARTS OF ACCESSES TO BE MAINTAINED AT THE EXPENSE OF THE UNDERTAKER
PART 2 THOSE WORKS TO RESTORE TEMPORARY ACCESSES WHICH WILL BE MAINTAINED AT THE PUBLIC EXPENSE
PART 3 THOSE WORKS TO RESTORE TEMPORARY ACCESSES WHICH WILL BE MAINTAINED BY THE STREET AUTHORITY
PART 4 THOSE PARTS OF ACCESSES TO BE MAINTAINED BY THE STREET AUTHORITY
TEMPORARY PROHIBITION OR RESTRICTION OF THE USE OF STREETS OR PUBLIC RIGHTS OF WAY
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
3.(1) The 1965 Act has effect for the compulsory acquisition...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
PART 1 FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS
PART 3 FOR THE PROTECTION OF THE RELEVANT PLANNING AUTHORITY
16.(1) The following provisions shall apply for the protection of...
17.Regardless of any provision in this Order or anything shown...
18.(1) Before beginning to construct any specified work, the undertaker...
19.The requirements which the consenting authority may make under paragraph...
20.(1) Subject to sub-paragraph (2), any specified work, and all...
21.(1) Subject to sub-paragraph (6) the undertaker shall, from the...
22.If by reason of the construction of any specified work...