Transitional and savings8.
(1)
Paragraph (2) applies where, before the day on which this Order comes into force, an application for an order granting development consent for the construction or extension of an onshore generating station that generates electricity from wind has been refused.
(2)
In such a case—
(a)
the provisions of the Act are to continue to apply to the refusal; and
(b)
if the refusal is overturned on a judicial review and an order granting development consent is made, article 7 of this Order applies as if development consent had been granted by an order made before the day on which this Order comes into force.