50.—(1) Utilities may use the negotiated procedure without prior call for competition in the following cases—

(a)where no tenders, no suitable tenders, no requests to participate or no suitable requests to participate have been submitted in response to a procedure with a prior call for competition, provided that the initial conditions of the contract are not substantially altered;

(b)where a contract is purely for the purpose of research, experiment, study or development and not for the purpose of securing a profit or of recovering research and development costs, and insofar as the award of such contract does not prejudice the competitive award of subsequent contracts which do seek, in particular, those ends;

(c)where the works, supplies or services can be supplied only by a particular economic operator for any of the following reasons—

(i)the aim of the procurement is the creation or acquisition of a unique work of art or artistic performance;

(ii)competition is absent for technical reasons;

(iii)the protection of exclusive rights, including intellectual property rights,

but only in the case of paragraphs (ii) and (iii), where no reasonable alternative or substitute exists and the absence of competition is not the result of an artificial narrowing down of the parameters of the procurement;

(d)insofar as is strictly necessary where, for reasons of extreme urgency brought about by events unforeseeable by the utility, the time limits laid down for open procedures, restricted procedures and negotiated procedures with prior call for competition cannot be complied with;

(e)in the case of supply contracts for additional deliveries by the original supplier which are intended either as a partial replacement of supplies or installations or as the extension of existing supplies or installations, where a change of supplier would oblige the utility to acquire supplies having different technical characteristics which would result in incompatibility or disproportionate technical difficulties in operation and maintenance;

(f)for new works or services consisting in the repetition of similar works or services assigned to the contractor to which the same utility awarded an earlier contract, provided that such works or services conform to a basic project for which a first contract was awarded following a procedure in accordance with regulation 44(1) and (2);

(g)for supplies quoted and purchased on a commodity market;

(h)for bargain purchases, where it is possible to procure supplies by taking advantage of a particularly advantageous opportunity available for a very short time at a price considerably lower than normal market prices;

(i)for purchases of supplies or services under particularly advantageous conditions from either a supplier which is definitively winding up its business activities or the liquidator in an insolvency procedure, an arrangement with creditors or a similar procedure under national laws or regulations;

(j)where the service contract concerned—

(i)follows a design contest organised in accordance with these Regulations, and

(ii)is to be awarded, under the rules provided for in the design contest, to the winner or to one of the winners of that contest, provided that all the winners are invited to participate in the negotiations.

(2) For the purposes of paragraph (1)(a)—

(a)a tender shall be considered not to be suitable where it is irrelevant to the contract, being manifestly incapable, without substantial changes, of meeting the utility’s needs and requirements as specified in the procurement documents;

(b)a request for participation shall be considered not to be suitable where the economic operator concerned—

(i)is to be or may be excluded in accordance with regulation 78(1) or 80(1), or

(ii)does not meet the selection criteria.

(3) For the purposes of paragraph (1)(d), the circumstances invoked to justify extreme urgency must not in any event be attributable to the utility.

(4) For the purposes of paragraph (1)(f)—

(a)the basic project shall indicate the extent of the possible additional works or services and the conditions under which they will be awarded;

(b)as soon as the first contract is put up for tender, the possible use of the procedure shall be disclosed and the total estimated cost of subsequent works or services shall be taken into consideration by the utilities when they apply regulations 16 and 17.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources