48.—(1) Where regulation 47(1) applies, the contracting authority or utility must not enter into the concession contract before the end of the standstill period.
(2) Where the contracting authority or utility sends a regulation 47 notice to all the relevant economic operators by facsimile or electronic means, the standstill period ends at midnight at the end of the 10th day after the relevant sending date.
(3) Where the contracting authority or utility sends a regulation 47 notice to all the relevant economic operators only by other means, the standstill period ends at whichever of the following occurs first—
(a)midnight at the end of the 15th day after the relevant sending date;
(b)midnight at the end of 10th day after the date on which the last of the economic operators to receive such a notice receives it.
(4) In paragraphs (2) and (3), “the relevant sending date” means the date on which the regulation 47 notice is sent to the relevant economic operators, and if the notices are sent to different relevant economic operators on different dates, the relevant sending date is the date on which the last of the notices is sent.
(5) Where the contracting authority or utility sends the regulation 47 notice to one or more of the relevant economic operators by facsimile or electronic means and to the others by other means, the standstill period ends at whichever of the following two times occurs latest—
(a)midnight at the end of the 10th day after the date on which the last notice is sent by facsimile or electronic means;
(b)the time when whichever of the following occurs first—
(i)midnight at the end of the 15th day after the date on which the last notice is sent by other means;
(ii)midnight at the end of the 10th day after the date on which the last of the economic operators to receive a notice sent by any such other means receives it.
(6) In this regulation—
(a)“regulation 47 notice” means a notice given in accordance with regulation 47; and
(b)“relevant economic operators” means economic operators to which regulation 47 requires a notice to be sent.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: