13.—(1) The undertaker must, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—
(a)the conceptual surface water drainage system (document 2.7, 19th August 2014);
(b)the design and access statement (document 4.3, September 2014);
(c)the environmental statement (document 5.1, 19th August 2014);
(d)the existing site layout plan (document 2.5, August 2014);
(e)the land plan and site location plan (document 2.1, August 2014);
(f)the maximum parameters of works (document 2.18, 23rd March 2015);
(g)the outline construction environmental management plan (document 6.1, 19th August 2014);
(h)the outline landscaping plan (document 2.15, August 2014);
(i)the site layout and works plan (document 2.2, August 2014),
for certification that they are true copies of the plans or documents referred to in this Order.
(2) A plan or document so certified is admissible in proceedings as evidence of the contents of the document of which it is a copy.
Commencement Information
I1Art. 13 in force at 12.2.2016, see art. 1