SCHEDULE 1AUTHORISED DEVELOPMENT
PART 2Requirements
Gas pipeline and AGI6
1
No part of the authorised development comprising the gas pipeline and above ground installation may commence until—
a
details of the gas pipeline, and
b
details of the AGI, including in respect of fencing or other means of enclosure,
have been submitted to and approved in writing by the relevant planning authority.
2
The details approved under sub-paragraph (1) in relation to the gas pipeline must be implemented in accordance with the following thresholds—
Maximum diameter | 600 mm (nominal bore) |
3
The details approved under sub-paragraph (1) in relation to the AGI must be implemented in accordance with the following thresholds—
Maximum height of buildings, including security fence | 3 metres |