SCHEDULE 2Permitted development rights

PART 19Development by the Crown or for national security purposes

Class Q – development by the Crown relating to an emergency

Conditions

Q.1

Development is permitted by Class Q subject to the following conditions—

(a)

the developer must, as soon as practicable after commencing development, notify the local planning authority of that development; and

F1(b)

on or before the expiry of the period of 12 months beginning with the date on which the development began—

(i)

any use of that land for a purpose of Class Q ceases and any buildings, plant, machinery, structures and erections permitted by Class Q is removed; and

(ii)

the land is restored to its condition before the development took place, or to such other state as may be agreed in writing between the local planning authority and the developer,

unless permission for the development has been granted by virtue of any provision of this Schedule or on an application under Part 3 F2or Part 13 of the Act.