Changes over time for: Cross Heading: Class A – gas transporters

 Help about opening options

Changes to legislation:

The Town and Country Planning (General Permitted Development) (England) Order 2015, Cross Heading: Class A – gas transporters is up to date with all changes known to be in force on or before 25 May 2025. There are changes that may be brought into force at a future date. Changes that have been made appear in the content and are referenced with annotations. Help about Changes to Legislation

Class A – gas transportersE+W

Permitted developmentE+W

A.  Development by a gas transporter required for the purposes of its undertaking consisting of—

(a)the laying underground of mains, pipes or other apparatus;

(b)the installation in a gas distribution system of apparatus for measuring, recording, controlling or varying the pressure, flow or volume of gas, and structures for housing such apparatus;

(c)the construction in any storage area or protective area specified in an order made under section 4 of the Gas Act 1965 (storage authorisation orders)M1, of boreholes, and the erection or construction in any such area of any plant or machinery required in connection with the construction of such boreholes;

(d)the placing and storage on land of pipes and other apparatus to be included in a main or pipe which is being or is about to be laid or constructed in pursuance of planning permission granted or deemed to be granted under Part 3 [F1(control over development) or Part 13 (application of Act to Crown land) of the Act];

(e)the erection on operational land of the gas transporter of a building solely for the protection of plant or machinery;

(f)any other development carried out in, on, over or under the operational land of the gas transporter.

Textual Amendments

Marginal Citations

M11965 c. 36; relevant amendments are made by section 67 of, and Schedule 7 to, the Gas Act 1986 (c. 44), Schedule 2 to the Planning (Consequential Provisions) Act 1990 (c.11), Schedule 4 to the Gas Act 1995 (c. 45) and Schedule 2 to the Planning Act 2008 (c. 29). See section 5(1) of the Gas Act 1965 for the meaning of storage area and protective area.

Development not permittedE+W

A.1  Development is not permitted by Class A if—

(a)in the case of any Class A(b) development involving the installation of a structure for housing apparatus exceeding 29 cubic metres in capacity, that installation would be carried out at or above ground level, or under a highway used by vehicular traffic;

(b)in the case of any Class A(c) development—

(i)the borehole is shown in an order approved by the Secretary of State for the purpose of section 4(6) of the Gas Act 1965; or

(ii)any plant or machinery would exceed 6 metres in height;

(c)in the case of any Class A(e) development, the building would exceed 15 metres in height; or

(d)in the case of any Class A(f) development—

(i)it would consist of or include the erection of a building, or the reconstruction or alteration of a building where its design or external appearance would be materially affected;

(ii)it would involve the installation of plant or machinery exceeding 15 metres in height, or capable without the carrying out of additional works of being extended to a height exceeding 15 metres; or

(iii)it would consist of or include the replacement of any plant or machinery, by plant or machinery exceeding 15 metres in height or exceeding the height of the plant or machinery replaced, whichever is the greater.

ConditionsE+W

A.2  Development is permitted by Class A subject to the following conditions—

(a)in the case of any Class A(a) development, not less than 8 weeks before the beginning of operations to lay a notifiable pipe-line, the gas transporter must give notice in writing to the local planning authority of its intention to carry out that development, identifying the land under which the pipe-line is to be laid;

(b)in the case of any Class A(d) development, on completion of the laying or construction of the main or pipe, or at the expiry of a period of 9 months from the beginning of the development, whichever is the sooner, any pipes or other apparatus still stored on the land are removed and the land restored as soon as reasonably practicable to its condition before the development took place (or to any other condition which may be agreed with the local planning authority); and

(c)in the case of any Class A(e) development, approval of the details of the design and external appearance of the building must be obtained, before the development is begun, from—

(i)in Greater London or a metropolitan county, the local planning authority,

(ii)in a National Park, outside a metropolitan county, the county planning authority,

(iii)in any other case, the district planning authority M2.

Marginal Citations

M2See section 1(1) of the Act, which was amended by section 31 of the Greater London Authority Act 2007 (c. 24); there are other amendments not relevant to this Order.

Back to top

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Schedule

The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Schedule as a PDF

The Whole Schedule you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?