SCHEDULE 2Permitted development rights
PART 14Renewable energy
Class H – installation or alteration etc of wind turbine on domestic premises
ConditionsH
Development is permitted by Class H subject to the following conditions—
a
the blades of the wind turbine is made of non-reflective materials;
b
the wind turbine is, so far as practicable, sited so as to minimise its effect on the external appearance of the building;
c
the wind turbine is, so far as practicable, sited so as to minimise its effect on the amenity of the area; and
d
the wind turbine is removed as soon as reasonably practicable when no longer needed.