Class A – development by Historic England

Permitted development

A.  Development by or on behalf of Historic England(1), consisting of—

(a)the maintenance, repair or restoration of any building or monument;

(b)the erection of screens, fences or covers designed or intended to protect or safeguard any building or monument; or

(c)the carrying out of works to stabilise ground conditions by any cliff, watercourse or the coastline;

where such works are required for the purposes of securing the preservation of any building or monument.

Development not permitted

A.1  Development is not permitted by Class A(a) if the works involve the extension of the building or monument.

Condition

A.2  Except for development also falling within Class A(a), Class A(b) development is permitted subject to the condition that any structure erected in accordance with that permission is removed at the expiry of a period of 6 months (or such longer period as the local planning authority may agree in writing) from the date on which work to erect the structure was begun.

Interpretation of Class A

A.3  For the purposes of Class A, “building or monument” means any building or monument in the guardianship of Historic England or owned, controlled or managed by it.

(1)

Historic England is the name used by the Historic Buildings and Monuments Commission for England (a body established under section 32 of the National Heritage Act 1983 (c. 47)).

Back to top

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Schedule

The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Schedule as a PDF

The Whole Schedule you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?