PART 2 U.K.Client duties

Application to domestic clientsU.K.

7.—(1) Where the client is a domestic client the duties in regulations 4(1) to (7) and 6 must be carried out by—

(a)the contractor for a project where there is only one contractor;

(b)the principal contractor for a project where there is more than one contractor; or

(c)the principal designer where there is a written agreement that the principal designer will fulfil those duties.

(2) If a domestic client fails to make the appointments required by regulation 5—

(a)the designer in control of the pre-construction phase of the project is the principal designer;

(b)the contractor in control of the construction phase of the project is the principal contractor.

(3) Regulation 5(3) and (4) does not apply to a domestic client.