Power to acquire land
20.—(1) The Company may acquire compulsorily so much of the land shown on the land plan which is within the Order limits and is included in Schedule 7 (acquisition of land and of subsoil of land only and power to impose restrictive covenants) as may be required for the purposes of the authorised works and may use the land so acquired for those purposes or for any other purposes that are ancillary to its railway undertaking.
(2) This article is subject to article 23 (power to acquire subsoil only).