Surface and foul water drainageE+W
8.—(1) No authorised development comprised in numbered works 1, 2, 3, 5 and 7 shall be commenced until, for each numbered work, written details of the surface and foul water drainage strategy (including means of pollution control and measures designed to control surface water during construction) for construction and operational phases of the project have been submitted to and approved by the relevant planning authority, in consultation with the Environment Agency, such strategy to be in accordance with the principles set out in Section 5 of the flood risk assessment.
(2) The surface and foul water drainage system must be constructed in accordance with the approved details before the operational phase of that part of the authorised development commences.
Commencement Information
I1Sch. 2 para. 8 in force at 14.8.2015, see art. 1